Streetcar Forum Lacked Fireworks But Revealed Substance

About 150 people crammed into Walter Reed Community Center last night to discuss the current state of planning for the Columbia Pike streetcar project.

Planners revealed that the streetcar line is expect to go into service in 2016 and is expected to cost $160 million to build. Of that, Arlington will pay $135 million and Fairfax County will pay $25 million, according to planners. However, county staff warned those cost estimates will change as further planning is done. The Pike Transit Initiative, as the project is called, is also seeking funding from the Federal Transit Administration, which could cover part of the cost of construction.

The streetcar would travel east from Skyline/Bailey’s Crossroads, down Columbia Pike, past the Air Force Memorial to end at South Eads Street. The plan also calls for one of two extensions to be built, either to the NOVA Community College campus near Skyline or to Long Bridge Park, near the Pentagon, to accommodate a streetcar storage and maintenance shed.

The public forum was expected to be contentious, as a number of streetcar critics had announced in advance they would attend. There were no fireworks or shouting matches, but during a question and answer session a few people did pelt planners with questions about the value of having a streetcar line at all.

Steven Del Giudice, head of transit operations and planning for Arlington County, suggested that there were other means for critics to express their dissent and that this meeting was “not the forum” to discuss the value of having streetcars on the Pike.

“Reasonable people can disagree,” said Del Giudice after the meeting, shrugging off the criticism.

Streetcar skeptic and Pike resident John Antonelli said he was concerned about the project’s cost, which some critics believe could reach past $300 million (Del Giudice disputed this, saying a quoted $336 million figure included 30 years of operating costs).

Antonelli argued the streetcar won’t save much money on existing bus service (Del Giudice says it will likely eliminate two to three bus lines), and noted that service could easily be disrupted by road repairs, a traffic accident, or a stalled car. He called the forum “a typical Kabuki theatre Arlington meeting.”

“The impression I got was ‘thank you for you comments, we will now do what we want to do,'” Antonelli said.

Still, most of the audience seemed supportive of the project. During the break-out session, attendees huddled over maps of the Pike with streetcar project staff to suggest station placements and other ideas and modifications of the plan.

The next phase of the project will be an environmental assessment of the line and all of its proposed options.

In order to comply with federal law when completing the assessment, the county will look at alternative options for each section of the proposed streetcar line. The options are: “do nothing,” which would leave the Pike essentially in the condition it’s in today; “low cost,” which would incorporate significant improvements to the bus lines going through the Pike; and the full “streetcar option.” The county expects to have the assessment done by spring 2011.

The author runs the People-Powered Arlington blog. Rendering via Pike Transit Initiative.

Recent Stories

Good Wednesday evening, Arlington. Let’s take a look back at today’s stories and a look forward to tomorrow’s event calendar. 🕗 News recap The following articles were published earlier today…

Arlington is receiving nearly $300,000 in federal funds to help clean up the Chesapeake Bay. The money is part of a much larger $206 million federal grant given to the National…

Schedule your tour today to see The Grace and Reva residences in National Landing. Located in the heart of the neighborhood’s vibrant food scene on Crystal Drive, these two residential…

James Beard semifinalist Peter Chang’s second restaurant in Arlington is expected to open next month in Crystal City. Located at 1550 Crystal Drive, the Chinese restaurant NiHao initially planned to…

Award-winning drag queen Tara Hoot is bringing her Family Fun Story Time Brunch to Arlington at Freddie’s Beach Bar! Saturday April 6 at noon! Join Tara for songs, stories, puppets, bubbles and joy! It’s not just stories, it’s a SHOW that’s perfect for kids and kids at heart–fun for everyone! Plus a tasty brunch at Freddie’s! Click the link and make your reservations now! ❤️ 🫧 🌈

Submit your own Announcement here.

The Summer 2024 STEAM (Science/Technology/Engineering/Arts/Math) Fellowship application is now open! Apply by April 15 to be considered!

The STEAM Workforce Development Teacher Fellowship provides Arlington Public Schools (APS) high school, middle school, and elementary school teachers with opportunities to learn about workplace needs in STEAM-related fields and for them to use the experience to enhance student learning to match workplace expectations in a selected industry. STEAM Fellows participate in a three-week summer fellowship, receiving a $4,000 stipend upon completion.

Applicants planning to pursue a fellowship in the arts must demonstrate how they will build connections between the arts and science, technology, engineering, or mathematics.

Click the button to learn more, share, apply, and see the variety of fellowships completed in previous years.

Read More

Submit your own Announcement here.

ACFCU’s Homebuying 101: Steps to Getting Pre-Approved

Are you ready to jump into homeownership, or have you started considering it but don’t know where to start?

Financial preparation is key when thinking about purchasing your first home and the first step to getting pre-approved. Join ACFCU for

Free Right-Sizing Workshop – How to Get Rid of Your…

Cody Chance and Dick Nathan of Long & Foster are hosting a free workshop at our office on Cherry Hill Rd. (formerly Lee Highway) on the topic of “down-sizing” Thursday, March 28 from 5:30-7:30. We have created a workbook with

×

Subscribe to our mailing list