Another Portion of Crystal Drive to Open for Two-Way Traffic

Update on 8/5/13 — The two-way conversion has been delayed until Wednesday.

Starting Monday afternoon, another section of Crystal Drive in Crystal City will be open for two-way traffic.

This weekend, crews with the Department of Environmental Services are expected to finish the final painting and striping on Crystal Drive between 12th and 15th Street S.

The striping is the second-to-last step of the project to make the Crystal Drive corridor open to two-way traffic. The last step is waiting for Dominion Power to energize the traffic signal at S. Clark and 12th Streets. Until that happens, S. Clark and 14th Streets will remain southbound only, DES spokeswoman Laura G. Smith said.

Striping work was underway Friday afternoon and will continue through Saturday and from 9:00 a.m. to 4:00 p.m. Monday. After 4:00 p.m. Monday, DES expects the stretch of road to open for two-way traffic. Parking is prohibited on Crystal Drive and 12th Street S. while crews are painting.