Traffic

Traffic Delays Possible on Williamsburg Blvd Due to Water Main Construction

Traffic delays are expected on Williamsburg Blvd as the county builds a new water main under the road.

“The County is building new water mains and modifying pipes to the Minor Hill Reservoir site and its four underground storage tanks. The projects will improve the water system’s reliability and redundancy at our most critical and largest water storage area,” said county spokeswoman Jessica Baxter.

Construction is scheduled to start today on southbound Williamsburg Blvd. at N. Sycamore Street, Baxter said.

There are potential traffic delays, as the county will be narrowing the existing travel lane to allow for the water main installation. Southbound traffic will be affected for eight to 12 weeks, according to a press release.

The county will also be closing a gap in the water main that runs under westbound Williamsburg Blvd between N. Frederick and N. Harrison Streets.

The westbound lane will be closed to traffic until summer of 2016 while crews work on the water main, according to the county. Cars will be routed around the construction using a part of the eastbound lane on Williamsburg Blvd.

There is no set date for when the county will start working on the main line under the westbound lane, Baxter said.

“Earliest anticipated start date would be Sept. 21, but we’ll update the community when a date is confirmed,” she said.

The water main project will cost $4.1 million and will come from the county’s utility fund, according to the press release. Once the water main line construction is completed, water will be able to flow through storage tanks easier, resulting in fresher water from the tap, the county said.

“The projects will boost the water system’s reliability and redundancy by providing a backup main to our most critical and largest water storage area,” said the press release.

Photos via Google Maps