The first SafeTrack maintenance surge, between Ballston and East Falls Church, is ahead of schedule, Metro GM Paul Wiedefeld announced today.
At the end of the day Monday, 96 percent of the planned work had been completed, with three days remaining in the schedule, Wiedefeld said. Continuous single-tracking on the Orange and Silver lines is still slated to wrap up tomorrow (Thursday), as originally planned.