Progress Amid Delays for The Board Room in Clarendon

The owners of the The Board Room in D.C. had hoped to unveil their Arlington location in the old Sehkraft Brewing spot last month, but construction delays are pushing back the opening of the Clarendon bar and entertainment venue.

Mark Handwerger, the owner of The Board Room’s parent company, Bedrock Bars, wrote in an email, “We are not exactly pleased by the delays.” But he said that The Board Room’s team is “holding everyone’s feet to the fire.”

Part of the issue has been a hold-up on the millwork, delivery and installation of two additional bars. The owners ultimately had to resort to out-of-town fabricators because “everyone within a couple hundred miles of D.C. is buried with other projects, most notably The Wharf,” Handwerger said.

Today an ARLnow reporter visited 925 N. Garfield Street and observed a couple workers inside the demolished bar space, although not a lot of heavy duty construction was taking place. Some of the wall murals have been painted over and new drywall is piled nearby. There’s also a lot of debris and building material staged to be hauled away.

The new goal is for The Board Room to open mid-November if everything goes smoothly.