Walter Reed Drive Project Aims to Improve Pedestrian, Bicyclist Safety

Enhanced crosswalks and curb extensions are coming to S. Walter Reed Drive, just south of Columbia Pike, in an effort to calm traffic and improve intersections for pedestrians and bicyclists.

Storm sewer upgrades and raised medians will also be added to the stretch of S. Walter Reed Drive between 11th Street S. and 13th Street S. The current “bike boulevard” will move from 12th Street S. to 11th Street S. between S. Highland Street and S. Cleveland Street.

County Manager Mark Schwartz has recommended awarding the project to Fort Myer Construction, headquartered in Washington. The County Board is scheduled to consider the contract at its Saturday meeting. The contract cost is $444,575.11, with a change order contingency allocation of $88,915.02.