Search Results for "columbia pike million utilit"
Arlington County is applying for regional funding to run buses every six minutes between Fairfax County and Amazon’s second headquarters in Pentagon City during peak hours.
The Arlington County Board on Saturday authorized staff to apply for up to $8 million in Northern Virginia Transportation Commission funding. Funding would offset the operating costs associated with running 10 buses per hour during peak times for two years along a new Metrobus route dubbed the 16M, connecting the Skyline complex in the Bailey’s Crossroads area of Fairfax County down Columbia Pike, to Pentagon City and Crystal City.
The report suggests that the county is preparing for an increase in ridership after the opening of the first phase of Amazon’s HQ2, despite work from home trends.
“The 16M service will provide a direct connection to Amazon HQ2 with its first phase of construction (2.1 million square feet of commercial space) coming on-line in Summer/Fall 2023,” per a county report. “This service will also take advantage of the recently built portions of Columbia Pike and [eight] new transit stations located on Columbia Pike.”
But recommendations to increase frequency along this route date back well beyond Amazon’s decision to move into Arlington, says Dept. of Environmental Services spokeswoman Claudia Pors.
She says the request acts on a 2016 study, which “recommended creating a route connecting Skyline with Crystal City through Columbia Pike in anticipation of growth in Crystal City.” That followed the cancellation of the Columbia Pike streetcar project, which would have followed largely the same route.
“The study evaluated ridership forecasting, current service patterns, like bus and seat availability, and travel patterns, like trip lengths, ridership rates and traffic volume in the area to make the recommendation to increase frequency,” Pors said.
Sometime this spring, the new 16M route will begin revenue service with a base frequency of buses every 12 minutes during the service day. The new route will replace existing 16G/H service.
Pors said the average weekday ridership for the last four-and-a-half years along the 16G/H line peaked at a little over 4,500 average weekday riders before Covid, and is now about 60% recovered compared to pre-pandemic levels.
The $38 million transformation of the Washington-Liberty annex is nearly complete.
Over the last three years, the nearly six-decade-old Arlington Education Center has undergone a complete overhaul to turn it into classrooms and school space for the burgeoning student body. This is the most significant renovation in the history of the building, which was completed in 1969 and previously used as the Arlington Public Schools headquarters. (The APS administrative offices are now located at Sequoia Plaza.)
We received an exclusive tour yesterday of the newly updated facility that is now updated classrooms, breakout areas, science labs, art studios, weight rooms, offices, and flex space. The project reached substantial completion back in June. With school less than two weeks away, it’s now all touch-ups, paneling, and inspections.
The annex is expected to open to students when the new school year starts later this month.
The goal of the project, APS’s director of design and construction Jeff Chambers told ARLnow while walking through the still-pristine hallways, was to turn an under-used office building into usable, updated school space.
“With this building, it’s set up so that it can be used for any type of classroom or for any grade,” Chambers said. “It’s going to be used by Washington-Liberty students when it opens, but it can be converted to be used for anything. The whole intent is that all of the classrooms can be modified and used for whatever program absolutely needs them.”
The five-floor, 55,000-square-foot facility can accommodate between 500 and 600 students. The building is shaped like a “quarter of a donut,” as described by project manager Robin Hodges, which allows nearly all of the classrooms a view of the outside while also facing inward towards the common areas.
Each level, with the exception of the ground floor, is similar in set-up, with the elevators moved back, large windows, and a common area with seating and furniture. The building’s footprint wasn’t expanded, though it might look that way.
“The ambient light into the classrooms and spaces has really made a huge improvement, opened up the building a lot more,” said Hodges. “Everyone that used to be here before and now walks the halls ask, ‘Did you make it bigger?’ No. We just have more daylight in the building.”
Chambers compared the old building’s lack of sunlight and darkness, particularly in the bathrooms, to walking into a famed Arlington landmark.
“It was like walking into The Broiler on Columbia [Pike] and you’re looking for your steak and cheese,” he said laughing, noting that they did a simulation of the sun’s movement and added window frits to help diffuse sunlight throughout the building.
It might now be an empty grassy space off of Columbia Pike, but in a few months this site will be home to a giant white spike that serves as a gateway to Arlington County.
Construction is set to begin at the southwest corner of Columbia Pike and S. Jefferson Street on The Pike, a large-scale piece of public art first commissioned nearly a decade ago. The sculpture is expected to be completed by the spring.
Foundation work is first up, beginning with surveying and site utility checks, Jim Byers of Arlington Cultural Affairs tells ARLnow.
Construction starts this week on foundation for @ARL_arts public art sculpture at Columbia Pike and S Jefferson. Most work will be 9am-4pm weekdays. Expect intermittent lane sidewalk closures. "The Pike" will be installed by spring. https://t.co/eNz0cKsC8Z pic.twitter.com/nsRqfagRhN
— Arlington Department of Environmental Services (@ArlingtonDES) November 15, 2021
To facilitate the work, there will be intermittent lane and sidewalk closures on both Columbia Pike and S. Jefferson Street. Construction will “generally” be between 9 a.m. to 4 p.m. Monday through Friday.
“Weather permitting, construction of the foundation is anticipated to be complete in December,” writes Byers.
After the completion of the foundation and a month-long concrete curing process, the sculpture itself will be installed. That’s expected to happen in early 2022.
The Pike will become part of the Arlington Public Arts’ permanent collection.
The sculpture is being made from a “reclaimed 50-foot tall wind turbine wing” and is supposed to represent a toll gate, in homage to when Columbia Pike was a toll road. The artwork’s location near the border of Arlington and Fairfax counties serves as a representative “gateway,” the county says.
The base of the sculpture will be studded with nearly 5,000 coins from all over the world, collected from county residents. The coins are another nod to Columbia Pike’s history as a toll road.
The Pike will also have lights around its base to illuminate it at night.
The sculpture was designed by Donald Lipski, who in 2017 explained he was inspired by wind turbines, toll gates, and the pike as a spear-like weapon.
“It’s just put up as this big beautiful thing. It’s a found object, it’s recycled, it’s emblematic of wind energy, it’s emblematic of a Pike, but one that’s vertical, one that’s in the open position and says, ‘Come on in. Everybody is welcome. You don’t have to pay a toll even though it used to be a Pike’,” Lipski said at a talk at the Columbia Pike Library at the time.
Back then, there were some objections to the process and design. The Arlington Mill Civic Association criticized the lack of public input and the Douglas Park Civic Association president noted that a blade and a toll gate were not great community representations.
Columbia Pike resident and ARLnow opinion columnist Chris Slatt, meanwhile, opined on Twitter that The Pike follows what appears to be the county’s preference for spikey, vertical sculptures which “would hurt King Kong if he stepped on it.”
See also: pic.twitter.com/7BItiHaq2F
— Chris Slatt (@alongthepike) November 15, 2021
The sculpture construction and installation has been included as part of the Columbia Pike Multimodal Improvement Project, a multi-year series of street improvements and utility upgrades along the entire stretch of roadway from the Fairfax border to just before the Pentagon.
The design, fabrication, and installation of The Pike is expected to cost about $250,000, writes Byers, “which is less than 1% of the total construction budget of $37 million for this portion of the Columbia Pike Multimodal Improvement Project.”
When the sculpture is completed next year, an celebration will be planned in coordination with the Columbia Pike Partnership.
(Updated at 4:30 p.m.) A multi-year project to improve transit along Columbia Pike has been delayed by design problems associated with the proposed bus shelters.
As a result, the first eight of 23 new transit stations, which the Department of Environmental Services was aiming to deliver this spring, will likely be installed next spring. In the meantime, temporary shelters have been installed at these locations, and bus service is set to return to half of them tomorrow (Friday).
The new stations comprise a $16.9 million project to transform the Pike into a “transit-oriented, pedestrian-friendly ‘Main Street,'” according to the county. The County Board approved the upgrades in the summer of 2018 as part of the 2019-2028 Capital Improvement Plan.
“New stations will make transit along the Pike easier, safer, more attractive and accessible — encouraging more people to use it,” the project webpage said.
The bus stop project dates back to the since-nixed plan for a Columbia Pike streetcar. A prototype stop, at the corner of the Pike and S. Walter Reed Drive, made national headlines after ARLnow revealed that it cost more than $1 million.

More recently, the station work has been stalled by structural flaws discovered with the bus shelters specially designed for the project, which feature a kit-of-parts design intended to cut down on costs compared to the custom-made $1 million “Super Stop.”
“Last November, our shelter fabricator, Future Systems, built a prototype of the shelter and identified stability issues with it,” said DES spokesman Eric Balliet. “After the design was revised, there were still concerns about its construct-ability and stability. These design issues were causing project costs to increase and further delays in delivery of the first stations.”
DES has opted to install prefabricated shelters from the same manufacturer, a decision supported by the County Board, which directed the department to finish these eight stations by the end of summer 2022. Choosing the prefabricated shelters will allow DES to finish those stations in spring 2022 instead of spring 2023, and will save more than $7 million, according to a recent report.

“By the end of the year, we expect to receive the final shelter drawings from Future Systems, to be followed in early 2022 with a Notice to Proceed for production and delivery of the first eight station shelters,” Balliet said. “Installation of shelters and amenities for the first eight stations is expected in spring 2022.”
The prefabricated shelters maintain some of the original shelter’s features — glass finishing, protection against bad weather and real-time bus arrival displays — and will have equivalent or more seating. The shelters are also shallower, giving pedestrians more room.
When finished, the stations will be accessible to people with disabilities and will have platforms that can fit two buses.

Construction to realign the eastern end of Columbia Pike, which is part of the project to expand Arlington National Cemetery, is expected to start soon.
The Arlington National Cemetery Defense Access Roads (ANC DAR) Project will realign Columbia Pike from east of S. Oak Street to Washington Blvd (Route 27). It will also modify the S. Joyce Street intersection, change the Columbia Pike and Washington Blvd interchange, and replace Southgate Road with an added segment of S. Nash Street.
Because of this, and as of early last month, parking is now permanently prohibited on Southgate Road between S. Oak Street and Columbia Pike.
Construction is expected to start in the early fall and be completed within four years, by summer of 2025, a Federal Highway Administration (FHWA) spokesperson tells ARLnow. This timeline is slightly pushed back from what’s listed on the FHWA project page.
The project will also add a new sidewalk and a shared-use trail, improve bicycle facilities, add street lighting, and put utility lines underground. FHWA’s project page also notes that the work done will be consistent with Arlington County Master Transportation Plan and Columbia Pike Multimodal Street Improvements Project. No residents will be displaced, though construction may bring added noise and traffic disruptions to the nearby Foxcroft Heights neighborhood.
All of this is being done to accommodate a 70 acre southern expansion of Arlington National Cemetery. It will add about 60,00 burial sites, including an above-ground columbarium, which will allow the cemetery to continue burials through the 2050s. The expansion will also bring the Air Force Memorial within cemetery grounds.
This project, particularly the modification of the Columbia Pike and Washington Blvd interchange, will also provide space for the 9/11 Pentagon Memorial Visitor Education Center. Construction on that is expected to start late 2023 with a completion set for two years later.

While this realignment project has been long awaited, it hasn’t happened without some proverbial bumps in the road. Initially, the Army proposed a land exchange agreement with the county where the federal government would acquire the land from the county that was needed for the expansion. In exchange, the county would get “all land south of a realigned Columbia Pike to meet a variety of public facility needs.”
But, in 2017, the Army decided against the land exchange agreement, leaving the county “disappointed.”
Then, last summer, the federal government filed a civil suit to claim through eminent domain nine acres of land from Arlington County. The feds offered the county $10 for the land, but Arlington County Attorney Steve MacIsaac told DCist/WAMU in November 2020 that wasn’t going to cut it.
However, in January 2021, the Arlington County Board unanimously approved an agreement with the state, the Army, and the U.S. Department of Transportation that essentially provided the needed land in exchange for the feds paying for nearly all of the $60 million project. The county is only responsible for $500,000 to design a multi-use trail along Washington Blvd.
For most of the year, a stretch of Columbia Pike on the western end of Arlington County will be reduced to one lane in each direction.
During the extended closure, necessitated by utility work, drivers can expect significant delays during rush hour. Another impact: on left turns in the construction zone.
Following criticism of county officials for insufficient communication about the closure, Arlington’s television arm has released a video detailing the closure and the detours in place to move traffic around it.
After construction concludes, the video notes, the affected portion of Columbia Pike will have wider sidewalks and will no longer have overhead utility lines.
Utility work will force lane closures along Columbia Pike starting next week.
“Starting on or about Monday, Dec. 30, there will be new traffic patterns along the west end of Columbia Pike, in Arlington, which are expected to cause additional delays for those travelling through this area,” the county said in a press release. “The changes are necessary so the contractor for the Columbia Pike west end project can install a utility duct bank system beneath the eastbound lanes.”
Originally the utility undergrounding project was to have placed the aforementioned duct bank under the sidewalk, but a bundle of communication lines was unexpectedly found where it was supposed to go, necessitating the placement under the Pike itself — at the cost of lane closures and an extra $5.5 million.
The work will reduce the western end of Columbia Pike to one lane in each direction for most of 2020, though one additional eastbound lane will open during weekday morning rush hours.
Drivers are being encouraged to take alternate routes.
More from the press release:
Between South Jefferson Street and the Four Mile Run Bridge, sections of Columbia Pike will be reduced to one lane in each direction daily, including weekends. One additional lane will be open in the eastbound direction, heading toward DC, during weekday morning rush hours (7 am – 9:30 am).
This lane reduction is expected to remain in place for much of the next year. Substantial completion for the Columbia Pike west end project, including utility undergrounding and streetscape improvements, is anticipated for early 2021.
Alternate Routes
Traffic is expected to be affected in and around the immediate area. Drivers not heading to a residence, business or another destination in this area are encouraged to seek alternate routes to reduce road congestion.
Roadways that parallel Columbia Pike:
- Route 50/Arlington Boulevard
- Interstate 395
On Columbia Pike, options for travelling around the work zone include:
- For westbound traffic – Follow George Mason Drive north to Route 50/Arlington Boulevard or south to Route 7/Leesburg Pike
- For eastbound traffic – Follow Carlin Springs Road north to Route 50/Arlington Boulevard or south to Route 7/Leesburg Pike
An already pricey plan to place overhead utility lines underground along Columbia Pike is getting more expensive.
The Arlington County Board voted unanimously at its Tuesday meeting to approve boosting an existing $17.5 million contract for the work to $23 million — a $5.5 million increase — due to some unforeseen circumstances.
In a report to the Board, county staff said that its contractor, Fort Myer Construction Corporation (FMCC), encountered a mysteriously out-of-place underground duct bank — the conduit through which utility lines are placed — on a segment of the undergrounding work from S. Greenbrier Street to the Four Mile Run Bridge.
(FMCC’s contract is for one segment, from the county line to Four Mile Run, of the overall project.)
The rogue duct bank was adjacent to Columbia Pike, where a new duct bank containing the currently above-ground utility lines was to go. The county says it’s investigating why the existing duct bank, which is owned by Verizon, was not under the roadway as records indicated.
Given that the lines can no longer be placed next to the roadway, they will have to go under Columbia Pike, county staff said. That will require more extensive lane and intersection closures and occasional weekend detours — thus the extra expense.
At last night’s meeting Board members pushed for much of the disruptive work to be done at night, to prevent a traffic nightmare along the Pike during peak times.
“This is going to be a mess,” said Board member Libby Garvey.
More from the county staff report:
A third segment, Four Mile Run Bridge to South Jefferson Street (Segment H&I), started construction in early 2018. During construction of this segment, a previously unknown existing underground communications duct bank was encountered which required redesign to relocate the new underground combined electric-communications duct bank, and results in this request to increase to the construction contract.
FMCC completed the first part of the new duct bank between South Jefferson Street and South Greenbrier Street without issues. The initial excavation for the segment between South Greenbrier Street and Four Mile Run Bridge uncovered an existing underground communications duct bank in the location planned for the new duct bank (Figure 1). This conflict resulted in a revised design that places the duct bank in the roadway, making the work more complex as construction must contend with heavy traffic conditions. The overall duct length has increased because the new duct bank must be routed around many existing utilities. Additionally, the project was delayed due to the time necessary to complete the redesign. A contract change was negotiated with FMCC for the additional cost to install the redesigned underground duct bank and return the project back to the original substantial completion timeframe. The result of negotiations was an increase of $5,500,000.
Construction that is part of this contract change will require additional lane closures beyond those currently in effect today. These will vary depending on the phase of construction and will be communicated to the public in advance. Some left-turn restrictions will be implemented in phases at intersections and driveways and some intersections will require closures and detours where the work will occur on weekends. Access to driveways will be maintained throughout the project area and bus stops will be temporarily relocated and consolidated when impacted by construction.
During the engineering phase of the project, records showed the existing communications duct bank was inside the roadway with sufficient clearance for the planned new duct bank. An investigation is ongoing into the reason why the existing duct bank was found to be in a location that interfered with the new duct bank and will continue concurrently with construction of the revised design.
Map via Arlington County. Kalina Newman contributed to this report.
This regularly-scheduled sponsored Q&A column is written by Eli Tucker, Arlington-based Realtor and Rosslyn resident. Please submit your questions to him via email for response in future columns. Enjoy!
Question: How much interest has there been in Trafalgar Flats and do you think it’s a good investment?
Answer: Twelve months ago I introduced a new condo building off of Columbia Pike, Trafalgar Flats, by Pillars Development Group. Now that they’re near completion, I stopped by to take a look at the progress and talk to Rick Snider, Pillars’ VP of Planning & Design.
Impressive Design, Upgraded Finishes
Trafalgar Flats owners will be pleasantly surprised with the quality of the finishes; everything is upgraded well beyond what one expects at this price point.
It’s a modern design without being over-the-top and includes nice touches, like heavier interior doors, most builders skip. Instead of using standard bucket-style recessed lighting, they chose LED lights that lay flat against the ceiling (pictured below) for a minimalist look I expect will become a trend.
Strong Pre-Sales
Selling condos without a model isn’t easy so having 40% sold (33 of 78 units) already reinforces how starved Arlington is for new condos at a reasonable price (about half the cost of comparable units at Key & Nash).
To Pillars’ credit, their sales have been evenly distributed across each of the three types of units – Jr 1BR ($265k+), 1BR ($340k+), and 2BR/2BA ($475k+). I was particularly interested in how the Jr 1BR would sell because it’s a product that we don’t see much of around here; it turns out they made the right decision.
Trafalgar Flats will be complete, with a model unit, by the end of the year. Although that comes at the slowest time of the year for local real estate I expect the pace of sales to move quickly. I wouldn’t be surprised if they are sold out by March 2019, sooner if Amazon HQ2 announces their move to Arlington.
Investing Along Columbia Pike
Western Columbia Pike has a higher appreciation ceiling over the next 5-10 years than most Northern VA neighborhoods. It is primed for a shift in residential and commercial activity as the County’s Multimodal Street Improvement project reaches completion over the next few years, including improvements to underground utilities.
Just this year, major projects along western Columbia Pike have been announced or under construction including Trafalgar Flats, a new Pillars townhouse community, Centro Arlington (anchored by Harris Teeter), and Gilliam Place Apartments.
Thoughts From Pillars Development Executive
I spoke with Rick Snider, long-time Northern Virginia real estate Executive and VP of Planning & Design for Pillars, about Trafalgar Flats and his thoughts on development along Columbia Pike:
How did you choose this area over others to build TF? We were immediately attracted to this site when it came onto the market due to the ‘hole’ in the market relative to “For Sale” product versus “Rental”; we rightly anticipated that some nearby apartment renters would want to become new home owners, rather than purchase an older condo.
Are there other pockets of Northern Virginia or Arlington that you believe has similar appreciation potential? We like Columbia Pike and the market along it; we already have townhouse lots in planning nearby Trafalgar Flats to emphasize our interest in and commitment to this area, and are hopeful that our searches for additional land development opportunities in the area will be rewarded.
Where do you see Columbia Pike Development in three years and in seven years? When do you expect the biggest transition to take place along the Pike? The foundational change of course is found in the Multimodal Project which underscores Arlington County’s commitment to upgrade the infrastructure along this important corridor and to thereby not only improve existing residents’ quality of life, but also to attract additional developments like Trafalgar Flats, Centro Arlington and Gilliam Place.
Do you think Columbia Pike or Lee Highway will re-develop faster? If you had asked me this a couple of years ago, I would have weighed in on Lee Highway without hesitation, but I think that with the new developments underway and with the infrastructure improvements going in now and in the future that it becomes much more of a horse race; and I think that the price of housing, both for sale and rental, may well be the deciding factor that pushes the Pike ahead.
If you’d like a question answered in my weekly column, please send an email to [email protected]. To read any of my older posts, visit the blog section of my website at www.EliResidential.com. Call me directly at (703) 539-2529.
Eli Tucker is a licensed Realtor in Virginia, Washington DC, and Maryland with Real Living At Home, 2420 Wilson Blvd #101 Arlington, VA 22201, (202) 518-8781.
Work is progressing on the multiphase Columbia Pike utility undergrounding and streetscape improvement project.
The gas main relocation on Columbia Pike — between Four Mile Run and the Arlington/Fairfax line — is expected to be completed later this month, ending the pre-construction phase of the utility undergrounding that began in 2017. Northern Pipeline, Washington Gas’ contractor for the project, will coordinate with customers to change service over to the new gas mainline.
Drivers should expect traffic disruptions, lane closures, and possible left turn restrictions on Arlington’s western end of the Pike for the duration of the construction. This phase of the undergrounding project is expected to take three years to construct.
Three segments of the entire multimodal street project have already been completed. Another three construction segments have yet to begin, and the entire project is estimated to continue through 2021, according to Arlington’s Dept. of Environmental Services. Those three segments run from S. Wakefield Street to S. Oakland Street, from S. Garfield Street to S. Quinn Street, and from S. Orme Street to S. Joyce Street.
A DES press release stated that the work was intended to “make Columbia Pike a safer, more accessible route for all users.”
The $14.6 million construction contract, approved November 2017 by the County Board, also includes street improvements between Four Mile Run Bridge and S. Jefferson Street. Planned enhancements include wider sidewalks, upgraded traffic signals and street lights. Old water and sewer pipes will be replaced and overhead utilities will be buried.
An outdoor sculpture by Chicago-born Donald Lipski will be installed by Arlington’s Western Gateway, near Columbia Pike and South Jefferson Street, marking the entrance to Arlington from Fairfax County. Residents interested in email updates regarding the projects can sign up on the county’s project and planning website.
It has been four years since Arlington County and WMATA opened the infamous $1 million bus stop at the corner of Columbia Pike and Walter Reed Drive. So where are the rest of the upgraded transit stations planned for the Pike?
They’re coming, starting next year, the county says.
“The County Board approved $13.3 million for the planned 23 stations in Arlington’s FY 2017-2026 Capital Improvement Plan,” says a county webpage for the project. “Construction of the transit stations is expected to begin in 2018 and proceed in phases through 2021.”
“That schedule still holds,” Arlington Dept. of Environmental Services spokesman Eric Balliet confirmed to ARLnow.com on Monday. “Design of site-specific improvements for the first six stations is underway. Design and construction for the remaining stations will be coordinated with the County’s plans for Columbia Pike street improvements and utility undergrounding.”
The per-station cost is still pegged around $575,000, well under the cost of the original prototype station. Originally, the stations were planned to serve the Columbia Pike streetcar, but with that project’s cancellation the stations will now serve WMATA and ART buses.
County staff is expected to present proposed revisions to its Transit Development Plan for the Pike in the second quarter of this year, with possible improvements to bus service along the corridor.