County Hoping to Wrap Up Green Valley ‘Town Square’ Project By End of Year

It’s behind schedule, but John Robinson, Jr. Town Square in Green Valley should open by the time the calendar turns to 2022.

Formerly known as Nauck Town Square before it was renamed last year after a long-time Green Valley civic leader, the new public park is intended to be a central hub of activity in the neighborhood. It will feature an outdoor stage, a plaza, tables and other seating areas, at a construction cost of around $5 million.

Originally, after the construction contract was awarded in mid-2019, the project was expected to be complete by the end of last year. Given the pandemic and other factors, however, it is still in progress.

Some local residents have expressed concerns about a pause in construction activity, but a county spokeswoman said things should ramp back up soon.

“Arlington County is excited about the new John Robinson, Jr. Town Square, with a goal of opening by the end of this year,” Arlington Dept. of Community Planning, Housing and Development spokeswoman Elise Cleva told ARLnow last week. “At this time, County permitting is concluding, and the contractor should resume work by the end of the month.”

“There are some uncertainties about the timing of the utility relocation and some work will continue after the opening,” Cleva continued. “However, barring any unforeseen delays, we still anticipate that the town square should be open so visitors can enjoy the square and open space by the end of the year.”

Asked about the delays, Cleva cited several factors.

“There isn’t a single, simple cause for delay,” she said. “It’s a combination of factors stemming from the complexity of the project, which requires coordination among several County departments and external partners.”

Cleva called the project and its timely completion “a countywide priority.”

“The project, designed by the award-winning landscape architect and artist Walter Hood, is a countywide priority with multiple departments and includes road realignment and improvements, sidewalk and pedestrian enhancements, relocation of utilities, and public art,” she said.