Update on 4/2/20 — The repairs were completed and the roadway is back open.

Update at 4:50 p.m. — Walter Reed Drive is now closed in both directions while crews work to stop the leak and repair the line. 

Earlier: The southbound lanes of Walter Reed Drive are blocked due to a significant outdoor gas leak south of Columbia Pike.

The leak was reported shortly before 2:30 p.m., near the intersection of Walter Reed and 11th Street S. Arlington police and firefighters are on the scene.

Initial reports suggest a gas line larger than 2 inches was struck by a construction crew, prompting the closure and extra precautions. First responders are now checking natural gas levels on the ground floor of the adjacent apartment building while awaiting the arrival of Washington Gas.

0 Comments

Morning Notes

Man Arrested After Door Incident at DCA — “A passenger on a flight operated by Frontier Airlines was taken into custody at Reagan National Airport Saturday, after allegedly using the emergency slide to exit the airplane, officials said.” [Washington Post, Twitter]

Metrobus Rides Are Free, For Now — “To help stop the spread of the novel coronavirus, Metrobus riders will be required to board using the rear doors and will not have to tap their fare cards, according to a letter sent to employees Sunday.
The change, which begins Tuesday, means rides essentially are free.” [Washington Post]

Don’t Flush Wipes Down the Toilet — From Arlington County Board Chair Libby Garvey: “Do NOT put wipes, paper towels etc in the toilet! They severely damage water treatment.” [Twitter, CNN]

County Trying to Help Small Businesses — “To mitigate some of the challenges and hardships experienced by small businesses as a result of COVID-19 related closures and modifications, Arlington County is finding new ways to reach out to business owners with counsel, resources and other options.” [Arlington County]

County Offers Help with Utility Bills — “If you are struggling to pay a County utility bill (water/sewer/refuse) at this time, please call the DES Customer Contact Center at 703-228-5000, Monday-Friday, 7 a.m. to 7 p.m. You may be eligible for special payment arrangements without accrual of additional late fees.” [Twitter]

Coronavirus Fraud Task Force Formed — “In response to the increased threat of fraud presented by the coronavirus, federal and Virginia state law enforcement leaders announced today the formation of the Virginia Coronavirus Fraud Task Force.” [Press Release]

Marymount Mulls Commencement Alternatives — “This Wednesday, Marymount University announced to students, faculty and staff that the online-only class period that started this week will be extended through the end of the spring semester, including final exams. It was also decided that the traditional commencement ceremonies scheduled for May 2020 would be canceled.” [Press Release]

Overnight Lane Closures in Rosslyn — “N Lynn St, SB Lee Hwy and the ramps to and from I-66 in Rosslyn will see overnight work requiring lane closures or full closures Mon night 3/23 – Thu night 3/26 in relation to the Lynn St Esplanade project.” [VDOT, Twitter]

0 Comments

(Updated at 3:45 p.m.) Columbia Pike was blocked by a crash at S. Scott Street, near the Wellington Apartments, Thursday afternoon.

The crash happened around 2:45 p.m. Initial reports suggest that a vehicle flipped on its roof and one person was removed from it by firefighters.

A traffic light was felled by the crash. So far there’s no word on injuries nor on what caused the crash.

As of 3:45 p.m., one lane in each direction had reopened, but there was still debris in the center of the roadway, including the fallen traffic signal.

Arlington County turned off three traffic cameras in the area, thus deliberately hindering ability of ARLnow and other news outlets to report on the crash. The cameras remained off, even after the patient was extricated.

0 Comments

Update at 3:15 p.m. — All lanes are back open.

Earlier: The northbound lanes of S. Glebe Road are closed at S. Lang Street after a reported crash.

Police are working to reopen at least one of the lanes. For the time being, drivers are being detoured around the closure.

There was no immediate word as to the nature of the crash.

0 Comments

All lanes of westbound Route 50 are blocked at the crash-prone intersection with Park Drive in the Arlington Forest area.

The crash happened in rainy weather around 8:30 a.m. Traffic cameras show at least two vehicles that appear to be involved, including one in the middle of the westbound lanes — which firefighters are pushing off to the side.

Traffic is currently being diverted at the crash scene, but at least one lane is expected to reopen shortly.

There’s no word on injuries.

Update at 8:55 a.m. — One lane has reopened while first responders await tow trucks to remove the damaged vehicles from the side of the road.

0 Comments

Morning Notes

Lane Closures Near Ballston — Sewer relining work is closing the right-hand lane of portions of Fairfax Drive and Wilson Blvd in the Bluemont neighborhood, near Ballston. [Twitter]

Arlington’s Young Population Drives Trends — “One of the reasons Virginia’s Arlington County is consistently rated highest for health and fitness is because of its young demographic. Take Ballston, for example, where 47.7% of the adult population is between 25 and 44 years old.” [WTOP]

Courthouse Metro Rescue Makes National News — “We would like to thank @ABCWorldNews for broadcasting our rescue of a @wmata rider last Friday. The patient is in stable condition. If you find yourself on the tracks and are unable to exit, roll towards the platform side to the area of refuge.” [Twitter, ABC News]

Fort Myer Gate Temporarily Closed — “Attention DoD ID card holders: @JBMHH’s Old Post Chapel Gate that provides entry onto the base from Arlington National Cemetery will be temporarily closed beginning today through the end of April for construction.” [Twitter, Twitter]

Nearby: Proposed Arlandria Redevelopment — A “D.C. developer filed preliminary plans with Alexandria earlier this month for the project, looking to completely overhaul a Mount Vernon Avenue shopping center near Four Mile Run Park, now called Del Ray North. It’s currently home to a MOM’s Organic Market, but has seen a variety of retail vacancies recently.” [Washington Business Journal]

0 Comments

The Arlington County Board this weekend is set to consider a $4.5 million contract to rehabilitate an out-of-service water main in the middle of N. Glebe Road.

The 36-inch transmission main — the same size as the large pipe that burst and shut down N. Glebe Road near Chain Bridge in November — was placed out of service in 2013 due to concerns about a catastrophic failure. A transmission line was built parallel to it after a major water main break on N. Old Glebe Road in 2009 and is currently providing service to the area.

County officials say rehabbing the old main, which was built in 1972, will help provide redundancy in the county’s water system. Arlington’s water comes from the Washington Aqueduct in D.C., by way of pipes that cross the Potomac River at Chain Bridge then branch out to various parts of the county.

The project will run along N. Glebe Road from Old Glebe Road to Little Falls Road — a distance of about 0.8 miles. Residents should expect lane closures and daytime water service interruptions during the course of the project, the county staffers said in a report to the County Board.

The Board is expected to vote on the contract at its meeting this Saturday.

More from the staff report:

This contract is for the rehabilitation of a transmission main built in 1972 in the right-of-way of North Glebe Road between Old North Glebe Road and Little Falls Road. The transmission main was placed out of service due to a catastrophic failure in 2009. The proposed rehabilitation work will prevent the likely future failure of this transmission main and bring it back to service which will provide redundancy for the water main network.

The proposed transmission main rehabilitation is part of the Water Main Rehabilitation / Replacement program outlined in the Capital Improvement Plan. Inspection and evaluation of the existing transmission main subsequent to the November 2009 break revealed that the transmission main was subject to failure. Therefore, a 36″ transmission main was installed in parallel and the existing failing transmission main was placed out of service in 2013. The proposed rehabilitation work consists of lining the existing transmission main that was placed out of service and replacing some portions of it. The overall goal for the proposed rehabilitation is to reinstate the transmission main which is currently out of service and provide the required redundancy to meet water demand in the area. […]

The scope of this project involves the rehabilitation of existing infrastructure along the same corridor and the construction will cause some water services disruptions throughout the duration of the project. These disruptions will not be for an extended period. Traffic flow will be maintained throughout the project duration by keeping at least one lane open each direction during working hours throughout the project duration. The traffic impacts of the project have been communicated via the project website and through Civic Association presidents. Progress updates regarding the construction of the project will continue to be regularly provided to the communities via the two channels noted above.

Upon contract award and before the start of construction, a detailed letter about the project and construction schedule will be sent to the presidents of both Civic Associations and then be distributed to residents who will be directly impacted by the project. Additionally, water service disruptions will be coordinated with the affected residents in advance of any shutdowns. All shutdowns will be limited to construction hours during the work day.

0 Comments

A crash involving some 3-4 vehicles is currently blocking lanes on S. Glebe Road.

The multi-vehicle wreck was reported around 9:45 on S. Glebe Road near the Maserati dealership and the I-395 ramps. At least one lefthand lane is blocked in both directions at 26th Road S.

Police are on scene directing traffic, while medics evaluate at least one person for possible injuries.

Update at 11 a.m. — All lanes have reportedly reopened.

0 Comments

For most of the year, a stretch of Columbia Pike on the western end of Arlington County will be reduced to one lane in each direction.

During the extended closure, necessitated by utility work, drivers can expect significant delays during rush hour. Another impact: on left turns in the construction zone.

Following criticism of county officials for insufficient communication about the closure, Arlington’s television arm has released a video detailing the closure and the detours in place to move traffic around it.

After construction concludes, the video notes, the affected portion of Columbia Pike will have wider sidewalks and will no longer have overhead utility lines.

0 Comments

Morning Notes

New Security Measures at ANC — “Arlington National Cemetery is implementing heightened security measures after a U.S. airstrike killed a top Iranian general. The extra security will create longer lines at security checkpoints and delays… All visitors over the age of 16 will be required to show a valid state or government photo ID to enter by foot or car, Arlington National Cemetery says. Visitors aged 16 or 17 can show a school-issued ID.” [NBC 4, Twitter]

Office Building Above Rosslyn Safeway Sold — “An affiliate of The Meridian Group has paid $113.15 million for 1525 Wilson Blvd., a Rosslyn office building featuring the colorful sculpture of a dancing couple, after selling another building in the Arlington County office market last summer.” [Washington Business Journal]

Lee Highway Planning Update — “To mark the end of a year collecting ideas for the road’s ‘reimagining‘ by the nonprofit Lee Highway Alliance, its executive director, Ginger Brown, gave an update predicting that phase two — development of land-use and zoning ideas — could be ‘the most contentious.’ […] ‘Lee Highway is stuck in 1950s strip-mall zoning,’ Brown told a Dec. 19 breakfast group.” [Falls Church News-Press]

Local Shop Has Best Cheese Selection in the U.S.? — Arrowine, a long-time ARLnow sponsor, has the best wine selection in the D.C. area and possibly the best cheese selection in the country after its recent renovation, according to local restaurant reviewer Don Rockwell. [DCDining.com]

Pike Lane Closures Are Hurting Local Business — “An employee at Cinthia’s Bakery II on Columbia Pike said the restaurant is seeing a significant drop off in the number of customers and an increase in empty tables all due to the construction.” [WJLA]

Yorktown Boys Improve to 11-0 — “This is the new Yorktown basketball: Take the first available shot, press nonstop on defense, substitute in a whole new lineup every 90 seconds. It’s a strategy some other area schools have tried — Lake Braddock, most successfully — but few have perfected. And it has the Patriots, the worst team in their conference last season, undefeated at 11-0 after a dazzling 86-51 rout of Madison (6-5).” [Washington Post]

0 Comments

It won’t be nearly as disruptive as the year-long, round-the-clock lane closures on Columbia Pike, but VDOT is planning temporary closures on I-66 next week.

One lane of eastbound I-66 will be closed nightly — from 9:30 p.m. to 5 a.m. — in the East Falls Church area on Monday and Tuesday, the state transportation agency said. There will also be multiple, brief closures of Sycamore Street and eastbound I-66 during that time.

The closure will allow the installation of bridge girders as part of the project to add a lane to eastbound I-66 between the Dulles Connector Road and Ballston.

More from a VDOT press release:

Bridge girder installation to widen I-66 East will require multiple brief closures of Sycamore Street in Arlington during overnight hours on January 6 and 7. Additionally, the left lane of I-66 East will be closed while crews install six bridge girders as part of the I-66 Eastbound Widening Project.

Details:

  • The left lane of I-66 East will be closed from 9:30 p.m. to 5 a.m. on the nights of Monday, Jan. 6, and Tuesday, Jan. 7.
  • There will be a full 20-minute closure of I-66 East shortly after midnight the night of Monday, Jan. 6, so that girders can be delivered to the work area.
  • Vehicle and pedestrian traffic on Sycamore Street under I-66 will be stopped for up to 20 minutes at a time between midnight and 4 a.m. multiple times each night. Stoppages are planned for northbound traffic on the first night, then southbound traffic the second night.
  • Pedestrians will be directed to the opposite sidewalk to proceed through the work zone.

All work is weather dependent.

Drivers and pedestrians are urged to use caution and expect possible delays. Real-time traffic conditions and information is available at www.511virginia.org or through the 511 Virginia mobile app.

The I-66 Eastbound Widening Project will add a travel lane along four miles of eastbound I-66 and install approximately 12,000 linear feet of new and replacement noise barriers. The project also includes building a new bridge over Lee Highway (Route 29) for the Washington & Old Dominion (W&OD) Trail, and constructing a new direct access ramp from eastbound I-66 to the West Falls Church Metrorail Station at the Route 7 Interchange.

The additional eastbound lane is scheduled to open to traffic in fall 2020, and the overall project is expected to be complete in fall 2021. Learn more about the I-66 Eastbound Widening Project and sign up for project updates and lane closure alerts at Transform66.org.