Join

Route 50-Courthouse Road Interchange Nearly Complete

The interchange of Route 50, N. Courthouse Road and 10th Street Road is on the verge of opening for good.

According to Virginia Department of Transportation spokeswoman Jennifer McCord, the westbound Route 50 frontage road that gives drivers access to Courthouse Road and 10th Street is expected to open on Wednesday. The opening means all facets of the intersection — the ramps from Courthouse Road and 10th Street to Route 50 in both directions and the frontage road — will be open for traffic.

The $39 million project began construction in April 2011, and McCord said the last pieces, to be completed over the summer, will be “final punch list work that will require some daytime lane closures.” The project was originally projected to be finished by last fall, but the completion date was pushed back to this summer. Of the $39 million the project is said to have cost, Arlington County contributed $1 million and the rest came from state and federal sources.

In addition to the other changes, there will also be “a signalized ‘T’ intersection providing access from both directions of Fairfax Drive to the Courthouse Road ramp,” according to VDOT’s project page.

Recent Stories

Featured in the latest Just Listed is a 3 BD/2 BA home with a covered front porch. Explore the private backyard in the open house this Saturday from 11 a.m.-2 p.m. and Sunday from 1-4 p.m.

Seven years after the initial rollout of Arlington Public Schools’ digital learning initiative, and after a year of heavier use due to distance-learning, opinions on tech in schools remain divided….

It’s overcast and muggy right now, but it could be stormy later today in Arlington.

Amid a rise in coronavirus cases, community leaders and the Arlington County Public Health Division are continuing to find ways to target particular demographics for which more outreach is needed….

×

Subscribe to our mailing list