Route 50-Courthouse Road Interchange Nearly Complete

The interchange of Route 50, N. Courthouse Road and 10th Street Road is on the verge of opening for good.

According to Virginia Department of Transportation spokeswoman Jennifer McCord, the westbound Route 50 frontage road that gives drivers access to Courthouse Road and 10th Street is expected to open on Wednesday. The opening means all facets of the intersection — the ramps from Courthouse Road and 10th Street to Route 50 in both directions and the frontage road — will be open for traffic.

The $39 million project began construction in April 2011, and McCord said the last pieces, to be completed over the summer, will be “final punch list work that will require some daytime lane closures.” The project was originally projected to be finished by last fall, but the completion date was pushed back to this summer. Of the $39 million the project is said to have cost, Arlington County contributed $1 million and the rest came from state and federal sources.

In addition to the other changes, there will also be “a signalized ‘T’ intersection providing access from both directions of Fairfax Drive to the Courthouse Road ramp,” according to VDOT’s project page.

Recent Stories

Enjoy alpacas, farmers markets and more at the Loudoun County Spring Farm Tour May 21-22.

A local man raised nearly $2,000 holding a yard sale this past weekend to help children impacted by the war. Constantin a Ukrainian-American who lives in Arlington’s East Falls Church…

Cali is the newest Adoptable Pet of the Week who loves treats, watching Netflix and nose boops.

A new restorative justice program launched last week in Arlington, aimed at diverting those under the age of 26 from the criminal justice system. The “Heart of Safety” program, part…

×

Subscribe to our mailing list