Join Club

A severely eroded ditch along N. Glebe Road near Chain Bridge is set for some restoration work.

The Arlington County Board this weekend is expected to approve a contract of up to $1.2 million. At least part of that will be reimbursed by VDOT, which maintains the road.

The work follows a major water main break in November 2019, which damaged both the road and the roadside ditch.

More from a county staff report:

This project includes the restoration of the existing ditch located along the south side of North Glebe Road (Route 120) that was severely eroded following the 36” transmission water main break in November 2019. Arlington County Department of Environmental Services (DES,) Virginia Department of Transportation (VDOT) and the National Park Service (NPS) have partnered to implement this improvement and restoration project. The restoration includes 500 feet of the ditch downstream of the water main break and stabilization improvements for 1,000 feet of the ditch upstream of the break to be improved with Class II riprap, as well as new guardrail installation to replace a previous guardrail and temporary jersey wall and restoration of the Potomac Heritage National Scenic Trail, which crosses this ditch in the downstream segment underneath George Washington Memorial Parkway.

The work also includes tree removal and planting/seeding, erosion and sediment control, and all other related incidental work described and required in the contract documents. Most of the work is planned to be performed at night utilizing an overnight road closure of North Glebe Road as outlined in the VDOT approved Temporary Traffic Control Plan. VDOT is reimbursing the County for the construction costs of the improvements located upstream of the water main break.

The report goes on to note that the county hired a consultant, Wetland Studies and Solutions Inc., to develop the repair plan.

Additionally, the report says the accepted bid — from Fairfax-based Bright Construction Group — is 13% higher than an engineer’s estimate, likely owing to complications caused by the rugged terrain and the work area being on both National Park Service and VDOT property.

…it is believed that the bidders perceived more risk and challenges in these bid items, which we consider fair given the unique challenges of this project area, where the contractor will be working on an actively flowing stream channel on NPS Lands, as well as within the narrow shoulder of a two-lane undivided VDOT-owned arterial roadway, North Glebe Road (US Route 120), that carries approximately 11,000 vehicles per day. For the work on Federal Lands and in VDOT right-of-way, the contractor will have to comply with restrictive NPS and VDOT permit requirements and perform all restoration as per each agency’s specifications.

The Board is scheduled to vote on the contract during its meeting this Saturday.

2 Comment

Three years after studying a crash-prone stretch of Arlington Blvd, the Virginia Dept. of Transportation is moving forward with plans to make some improvements.

There will be a virtual meeting this Thursday on changes coming for a nearly mile-long stretch of Route 50 between Glebe Road and Fillmore Street. Construction is scheduled to begin in early 2030, VDOT spokesman Mike Murphy tells ARLnow.

The changes, based on study recommendations made in 2020, include building a raised median along Arlington Blvd and adding eastbound and westbound dedicated left-turn lanes at Irving Street.

Difficulty making left turns and a lack of dedicated left-turn lanes were a top concern for surveyed members of the public, says VDOT. Other top concerns included “aggressive driving.”

Currently, this segment of Route 50 averages 58,000 vehicles a day and has a median that ends just east of the Glebe Road underpass. It also has a few tricky intersections where drivers can turn left, such as at Irving Street. During rush hour, drivers going straight can be seen jumping around those turning left to avoid waiting for them to turn.

Beyond adding left-turn lanes at Irving Street, VDOT also plans to:

  • extend the eastbound and westbound left-turn lanes at Fillmore Street
  • extend the eastbound service road to connect existing driveways between S. Old Glebe Road and Jackson Street
  • extend the westbound service road to connect existing driveways between Irving Street and Jackson Street
  • Reconstruct portions of the shared-use paths on both sides of Arlington Blvd

The state transportation department is also mulling new lighting between Irving and Fillmore streets, on-street parking between Garfield and Fenwick streets and bus stop improvements.

These recommendations came from VDOT’s 2020 Strategically Targeted Affordable Roadway Solutions study. This assessed safety and operational upgrades for this segment of Route 50, which VDOT says experiences congestion during rush hour and a high number of crashes.

Crashes on Arlington Blvd between Fillmore Street and Glebe Road (via VDOT)

Within four months of the release of recommendations, the Arlington County Board endorsed an application for $25 million in grant money to realize these upgrades.

In 2021, the Commonwealth Transportation Board approved $29 million in Smart Scale funding for this project, Murphy says.

But the plan did not sit well with members of the county’s Transportation Commission. Downvoting the application, they argued VDOT did not evaluate how high speeds contribute to crashes or consider how to lower speeds, such as by narrowing lanes. County staff, meanwhile, sought the commission’s approval retroactively.

In a column subsequently written for ARLnow, Transportation Commission Chair Chris Slatt said the following:

VDOT’s decision to select a costly, construction-intensive capital project to solve the safety issues in this stretch means our community will be stuck with six to eight years of additional crashes, injuries and even fatalities when VDOT’s own study makes it clear that a the majority of the safety benefit of their preferred alternative could be implemented in the short-term, with temporary materials and a much lower cost.

Residents and road users can provide feedback through Thursday, Sept. 14.

5 Comments
Two-vehicle crash on Washington Blvd ramp in May (staff photo by Jay Westcott)

(Updated at 8:30 p.m.) The Virginia Dept. of Transportation is exploring potential upgrades for sections of Route 50 and Washington Blvd in Arlington in response to concerns about safety and congestion.

The department is urging residents and road users to share their feedback – via an online survey through Aug. 15. Possible improvements identified by VDOT include better bike and pedestrian access, improved safety at intersections, and traffic congestion management.

The study, conducted by VDOT as part of its Project Pipeline program, will assess three-quarters of a mile of Arlington Boulevard, from Fillmore Street to N. Pershing Drive, and about a mile of Washington Boulevard, between Columbia Pike and N. Pershing Drive. The study is expected to be complete by the summer of 2024.

Any potential project solutions that come from the study may be funded through various programs, including Smart Scale (a federally funded statewide program that allocates money to states every six years for transportation projects), Revenue Sharing, and interstate funding, among others.

“The Commonwealth is partnering with Arlington County to develop targeted improvements for the Route 50 and Route 27 study that minimize community impacts and address priority needs in a cost-effective way,” VDOT said in a press release Tuesday.

The study area includes some crash-prone ramps to and from Washington Blvd and Route 50.

In addition to the online survey, comments can be emailed to [email protected] or mailed to Khalil Minhas, P.E., Virginia Department of Transportation, 4975 Alliance Drive, Fairfax, VA 22030.

Route 50 and Route 27 study area (via VDOT)
0 Comments

VDOT has started planned rehabilitation work on a bridge over I-66.

The state transportation department says the 21st Street N. bridge, built in 1980, is “deteriorating” and needs concrete repairs and other TLC. The bridge is located near the Mom’s Organic Market along Langston Blvd; it connects drivers going between Courthouse, the North Highlands neighborhood, and Rosslyn.

The $4.1 million project will prompt some temporary lane closures on I-66 during construction, as well as temporary closures of a sidewalk along the bridge.

More, below, from a VDOT press release.

Work is underway to rehabilitate the 21st Street North bridge over I-66 to improve driver, bicyclist and pedestrian safety and extend the overall life of the bridge, according to the Virginia Department of Transportation. The bridge, located between the Spout Run Parkway (Exit 72) and eastbound I-66 Route 29 Rosslyn/Key Bridge (Exit 73) interchanges, was built in 1980.

The project includes:

  • Resurfacing the concrete bridge deck
  • Closing deck joints
  • Repairing concrete piers and abutments
  • Replacing bearings
  • The width of the existing lanes and sidewalks on the bridge will remain the same.

During construction:

  • Daytime lane closures may be scheduled along I-66 and 21st Street North
  • Overnight lane closures may be scheduled on I-66
  • When one sidewalk along the bridge is closed, pedestrians will be detoured to the sidewalk on the opposite side
  • The Custis Trail under the bridge will remain open to bicyclists and pedestrians
  • Parking will not be allowed on the bridge or approaches

Starting in mid-2024, 21st Street North will be temporarily reduced to one lane on the bridge and open to northbound traffic only. Further information will be provided closer to the start of the partial bridge closure, which will be in place for several months while work occurs on the bridge deck.

The $4.1 million 21st Street North over I-66 Bridge Rehabilitation Project is financed with federal and state funding, including State of Good Repair funds used for bridges. The project is scheduled for completion in late 2024.

Drivers, bicyclists and pedestrians are reminded to use caution when traveling in active work zones. Be alert to new traffic patterns and limit distractions.

0 Comments
Glebe Road study area (via VDOT)

Changes might eventually be coming to the busy stretch of Glebe Road between Columbia Pike and I-66 in Ballston.

The Virginia Dept. of Transportation today kicked off the public engagement process for a study of the state-maintained stretch of arterial roadway.

The study, which will take about a year and a half, is part of a VDOT program to “develop comprehensive, innovative transportation solutions to relieve congestion bottlenecks and solve critical traffic and safety challenges throughout the commonwealth.”

A new public survey for the study is open through Thursday, July 27. It notes that Glebe Road is a “major north-south travel corridor for Arlington County, and the segments in the study area are in the County’s High Injury Network.”

Crash with overturned vehicle and multiple injuries on N. Glebe Road in April 2022 (staff photo by Jay Westcott)

Earlier this year ARLnow reported that an intersection in the study area, S. Glebe Road and 9th Street S., was on tap to get some safety upgrades — potentially to include a traffic signal — in response to community concerns, particularly among cyclists.

VDOT said on its survey page that the study will only result in proposals and will not automatically lead to construction.

“This STARS (Strategically Targeted Affordable Roadway Solutions) study… will consider and develop potential safety and operational improvements for all users in the study area and develop cost estimates for the preferred alternatives,” the department said.

“The study will not set construction dates for any of the alternatives,” continued VDOT. “The purpose of this study is to develop proposed improvements that localities can pursue for funding, and to consider including in their comprehensive plans.”

The portion of Glebe Road being studied has been the scene of numerous crashes in recent memory, including a crash in the Ballston area that injured multiple people in April 2022.

More, below, from a VDOT press release.

The Virginia Department of Transportation is seeking feedback on a STARS (Strategically Targeted Affordable Roadway Solutions) study assessing potential safety, multimodal and operational improvements for over two miles of Glebe Road (Route 120) between Columbia Pike (Route 244) and I-66. Glebe Road averages about 29,000 vehicles a day within the study limits.

VDOT invites residents and travelers to take an online survey regarding corridor priorities. This feedback will be used to help develop improvement alternatives that will be evaluated and presented during another opportunity for public comment scheduled this fall.

The survey, which has a translation tool for Spanish and many other languages, is available at virginiadot.org/GlebeSTARS through July 27. Comments can also be sent to [email protected] or to Mr. Bobby Mangalath, P.E., Virginia Department of Transportation, 4975 Alliance Drive, Fairfax, VA 22030.

The study is expected to be completed this winter. It does not set construction dates for any improvements but develops proposed improvements that localities can pursue for funding.

VDOT ensures nondiscrimination and equal employment in all programs and activities in accordance with Title VI and Title VII of the Civil Rights Act of 1964. If you need more information or special assistance for persons with disabilities or limited English proficiency, contact VDOT Civil Rights at 703-259-1775.

0 Comments
A trail leading to VDOT-owned land near Chain Bridge Forest (via Google Maps)

(Updated at 9:15 a.m. on 7/12/23) A secluded wooded area south of Pimmit Run in North Arlington with a little-known history is up for sale and Arlington County could become the buyer.

The county is considering whether to buy a 6.7-acre parcel near the Chain Bridge Forest neighborhood from the Virginia Dept. of Transportation for $2.88 million. The property, between a curving section of N. Glebe Road and Pimmit Run, includes both developable and protected land.

VDOT originally intended to use it for a connector road from N. Glebe Road to Route 123 (Chain Bridge Road) in Fairfax County, which it never built, the county says. It now is giving Arlington first dibs before turning to private buyers. Should the sale go through, the county would set the land aside for public open space.

The property in question sits within the historic boundaries of a near-forgotten settlement by freed Black people who worked the land from the 1850s to the 1950s, according to the county and Jessica Kaplan, a local expert on and author of a definitive 2018 article about the community.

Kaplan pieced her article together from census data, deeds, wills, maps and claims residents made against the government for property it confiscated during the Civil War.

The settlement grew after John Jackson, a free Black man, bought three acres from white landowner William Walker, who he had known since childhood, shortly before the Civil War broke out, Kaplan writes. She says it is unclear if he sold to Jackson because of their friendship or because white people were not interested because it was a low-lying, flood-prone area.

Despite those issues, Jackson went through with the purchase. Walker’s initial sale sparked a small exodus of Black families — who had either escaped slavery, bought their freedom or were born free — from Fairfax County to what is now Arlington.

In what may be a riff on the problems with the land, residents called it “The Bottom,” Kaplan writes. At its peak, 20 families lived there.

“Whether [leasees] or owners, they found relative safety in numbers and in the secluded, timber-lined hollow of The Bottom,” she said. “The Bottom remained their home through challenging times: war, Reconstruction, Jim Crow, segregation, and suburbanization.”

The presumed borders of The Bottom and the VDOT property within it (via Arlington County)

Residents eked out a living farming, tending livestock and quarrying stone, she said. During the Civil War, men helped build nearby Fort Marcy and Fort Ethan Allen while women sold baked goods and did laundry for soldiers. Some of the Union soldiers, however, raided their farms and burned the land for fuel.

With paltry government repayments for confiscated property, the families built back after the war, Kaplan wrote. They farmed, quarried stone and worked for nearby white families. Their children walked three miles to attend the closest school for Black children, then called Sumner School.

The enclave dwindled to non-existence in the 1950s as residents died, moved to other Black neighborhoods in Arlington such as Halls Hill, or left the area. Economic pressures were compounded by access: Arlington County abandoned a road running along The Bottom’s west side and circumvented it with the new N. Glebe Road to Chain Bridge.

Investors ended up owning all the land comprising The Bottom, eventually selling to the U.S. government. Kaplan says the community “became the anchor for an overpass of the George Washington Memorial Parkway.”  Read More

2 Comments

Work is underway to make a 53-year-old bridge S. Abingdon Street bridge over I-395 safer and extend its overall life, per the Virginia Dept. of Transportation.

The 53-year-old bridge is located between the I-395 interchanges for King Street and Shirlington Circle in the Fairlington neighborhood. It was last rehabilitated in 1994 and is in need of attention, according to a press release from the state transportation department.

The planned repairs will use $8.4 million in federal and state funding and will wrap up in late 2024, the press release said.

Work includes rehabilitating the bridge deck, repairing deteriorating concrete, replacing all steel bearings and eliminating bridge joints, per a project overview video.

Arlington County also identified S. Abingdon Street, from 34th Street S. to Fire Station 7, for resurfacing. It is coordinating with the state on those changes, including a buffered bike lane to improve the cycling experience and narrower travel lanes to manage vehicle speeds.

Bridge deck rehabilitation work will last about 12 weeks and occur in three stages, the video says.

In the first phase, all traffic will be shifted to the east side of the bridge, with two shared bicycle and traffic lanes and one five-foot-wide sidewalk. A temporary crosswalk will be added near 36th Street S. In the second phase, all traffic will be shifted to west side of the bridge.

In the third stage, traffic will be split on both sides of the work zones and the crosswalk will be removed.

“When one sidewalk along the bridge is closed, pedestrians will be detoured to the sidewalk on the opposite side,” VDOT said in the press release. “Drivers, bicyclists and pedestrians are reminded to use caution when traveling in active work zones. Be alert to new traffic patterns and limit distractions.”

The I-395 main and express lanes may see periodic daytime and overnight lane closures, VDOT says.

“Most of the work below the bridge will be performed during nighttime operation to avoid impact to normal daytime traffic particularly peak hour traffic,” the project video says.

0 Comments

A sewer repair company put a price on dealing with federal and state agency permitting processes and working on high-traffic roadways.

That price tag is just over $2.6 million.

Arlington County is poised to pay that extra sum, conceding that the location of the project in question presents “unique challenges.”

To repair an “essential part” of the county’s sanitary sewer system — dubbed the Spout Run Deep Sewer Line — the selected contractor, AM-Liner East, will have to navigate distinct permitting processes and regulations for the National Park Service and the Virginia Dept. of Transportation.

This pipe carries “a significant amount of flow” from federally protected land, and along Langston Blvd and I-66, with the pipe reaching depths up to 115 feet below ground, according to the county.

After getting permission from NPS to work on protected parkland, the contractor will seek state permission once it hits I-66. It will be working on a narrow median and shoulder of I-66 and multiple travel lanes in both directions on Langston Blvd.

“It is believed that the bidders perceived significantly more risk in these bid items, which County staff consider fair given the unique challenges of this project area,” per the report.

For these reasons, AM-Liner East — the lowest responsible bidder — still exceeded expected project costs of $5.3 million. The Arlington County Board is scheduled to approve a $7.9 million contract, plus a $1.2 million contingency “for change orders or increased quantities,” at its upcoming Saturday meeting.

The proposed project generated what the county described as significant interest from nine contractors specializing in trenchless sewer rehabilitation. Only two bid on the project, however — a testament to its perceived challenges.

“For the work on federal lands and in VDOT right-of-way, the contractor will have to comply with restrictive NPS and VDOT permit requirements, respectively, and perform all restoration as per each agency’s specifications, which differ greatly from each other and from the County’s specifications,” the report said.

Arlington County says it identified this 86-year-old sewer line for repair in 2019 after a video inspection “revealed corrosion of the concrete pipe, indicated by exposed aggregate, exposed reinforcing steel, infiltration at the pipe joints, and small cracks.”

The project is part of the county’s program to rehabilitate critical large sewers, which are part of Arlington’s 465-mile sanitary sewage system. This project will start at Spout Run, north of the N. Courthouse Road cul-de-sac and end at N. Nash Street.

“This intricate network exists to make sure that the wastewater that gets flushed every day from homes and businesses makes its way to the Water Pollution Control Plant where it’s properly cleaned and treated before being recycled back into the environment,” the project webpage says.

For this project, AM-Liner East will use a trenchless technology known as cured-in-place pipe lining, which is seen as a relatively quick way to fix pipes with little or no digging involved.

A flexible liner is inserted into the pipe, inflated and exposed to heat or ultraviolet light to harden it and create a new, smooth surface inside.

To ensure this is done without disrupting existing flow, the contractor will install a temporary bypass. The bypass will be above-ground through residential grass areas along N. Uhle St, the Custis Trail and one lane of Langston Blvd. It will go underground near street crossings, such as at N. Scott, N. Quinn and N. Nash streets.

How the trenchless pipe repair technology ‘cured-in-place-piping’ works (via Arlington County)
0 Comments

Repairs are in progress on the bridge that takes traffic from southbound I-395 to Route 1 in the Crystal City area.

The $4 million Virginia Dept. of Transportation project will “improve safety and extend the overall life of the bridge,” which was originally built in 1976.

More from a VDOT press release:

Repairs are underway on the weight-restricted (20 tons) southbound I-395/Route 1 Exit 8C bridge, according to the Virginia Department of Transportation. The project will improve safety and extend the overall life of the bridge, which carries southbound Route 1 over the 395 Express Lanes, the northbound I-395 general purpose lanes and northbound Route 110.

The project includes retrofitting and spot painting structural steel, and replacing the catcher beam system and strip seal at the joint.

During the project, some day and overnight single-lane closures may be scheduled, along with occasional overnight full closures of the bridge with detours.

The bridge, which was originally built in 1976 and rehabilitated in 1999, is about a fifth of a mile long and averages 20,000 vehicles a day.

The $4 million project is financed with federal and state funding and is scheduled for completion in late 2023. […]

Drivers are reminded to use caution when traveling in active work zones. Be alert to new traffic patterns and limit distractions.

The entrance to the bridge has been the scene of numerous crashes caused by drivers trying to exit across multiple lanes at the last second, as documented by public safety watcher Dave Statter.

0 Comments
VDOT snow plow spreading salt on N. Glebe Read in 2021 (staff photo)

(Updated at 3:45 p.m.) A major storm affecting most of the eastern U.S. and midwest is set to ramp up tomorrow, making for hazardous holiday travel.

Ahead of the storm, the Virginia Dept. of Transportation sent a clear message this afternoon: start your trip now, if you can.

The storm will mostly bring the D.C. area copious amounts of rain starting Thursday morning, along with gusty winds and bitter cold temperatures on Friday. Frozen precipitation beyond some possible snow flurries is not expected in Arlington, but points west and north will likely see snow, sleet and freezing rain.

Along I-81 and the Blue Ridge, the storm is expected to be a high-impact event, and travel on Thursday is “not advised,” VDOT says.

More from a VDOT press release, below.

The Virginia Department of Transportation (VDOT) is advising motorists traveling in and through Virginia to adjust their holiday travel ahead of winter weather expected in parts of the Commonwealth beginning Wednesday night and continuing through Friday.

Travelers are advised to shift holiday travel to Wednesday if possible. Travel on Thursday is not advised, especially through the western regions of Virginia along the Interstate 81 corridor, to avoid potentially hazardous conditions created by forecasted winter weather.

According to current forecasts, wintry precipitation is expected to arrive as soon as 11 p.m. on Wednesday, Dec. 21 in the southwestern regions of the state, and move northward through the western third of the state, and into portions of northern Virginia through Thursday. Periods of heavy snow are expected along the northern sections of I-81 and the mountain passes including Interstate 64 over Afton Mountain and Rt. 33 between Standardsville and Harrisonburg early Thursday. Temperatures are expected to drop rapidly through the day on Friday leading to the potential for refreeze in areas where the pavement remains wet.

VDOT crews are pretreating roadways and interstates today in anticipation of the weather event.

With extreme low temperatures expected to move in Friday, motorists, if traveling, should pack an emergency kit and blankets, and have mobile devices fully charged in the event of a breakdown or emergency.

“Please continue to monitor forecasts closely as forecasts can improve or worsen quickly,” VDOT said in a separate advisory. “Drivers should expect roads to be impacted Thursday and Friday… Treat anything that looks wet as if it could be icy, especially bridges, ramps, overpasses, and elevated surfaces. If there is snow or ice on roadways, travel is hazardous.”

The transportation agency is currently pretreating roads and “will begin deploying trucks early Thursday morning to treat roads as needed.”

“Adjust travel plans and avoid all nonessential travel during the height of the storm,” VDOT said “This helps to avoid deteriorating conditions and to allow crews room to work.”

A Flood Watch, meanwhile, has been issued for the D.C. area ahead of the rain.

322 PM EST Wed Dec 21 2022

…FLOOD WATCH IN EFFECT FROM THURSDAY MORNING THROUGH LATE THURSDAY NIGHT…

* WHAT…Flooding caused by excessive rainfall is possible.

* WHERE…DC and portions of Maryland and northern Virginia, including the following areas: District of Columbia. In Maryland, Anne Arundel, Cecil, Central and Southeast Howard, Central and Southeast Montgomery, Prince Georges, Southeast Harford and Southern Baltimore. In northern Virginia, Arlington/Falls Church/Alexandria, Fairfax and Prince William/Manassas/Manassas Park.

* WHEN…From Thursday morning through late Thursday night.

* IMPACTS…Excessive runoff may result in flooding of rivers, creeks, streams, and other low-lying and flood-prone locations. Flooding may occur in poor drainage and urban areas.

* ADDITIONAL DETAILS…
– Moderate rainfall is expected Thursday into Thursday evening, with rainfall totals of one to two inches. This may lead to isolated instances of flooding, especially in urban and poor drainage areas.
– http://www.weather.gov/safety/flood

PRECAUTIONARY/PREPAREDNESS ACTIONS…

You should monitor later forecasts and be alert for possible Flood Warnings. Those living in areas prone to flooding should be prepared to take action should flooding develop.

VDOT released the following timeline of expected conditions in Northern Virginia and western zones through Christmas.

Read More

0 Comments
Ice / freezing rain on windshield (file photo)

Arlington Public Schools will open on a two-hour delay on Thursday due to expected freezing rain, the school system just announced.

APS follows Fairfax County Public Schools in announcing a two hour delay tonight. Other Northern Virginia districts have announced weather plans ranging from two hour delays to closures.

From APS:

CODE 2: All APS schools and offices will open two hours late Thursday, Dec. 15. The Extended Day program will also open two hours late and morning field trips are canceled. Custodial and maintenance staff and food service workers should report to work at their regularly scheduled time. All other employees should report to work two hours past their usual start time. For updates about Pool Operations, go to www.apsva.us/aquatics. For information about Arlington County operations go to www.arlingtonva.us.

More on the storm timing from the National Weather Service:

Metro, meanwhile, said today that it’s tracking the weather and will respond to hazardous conditions as necessary.

Metro is keeping an eye on the sky and advising customers to be prepared for potential service impacts to Metrobus service tomorrow, December 15, if icy conditions materialize.

Metrobus plans to provide regular scheduled service tomorrow. However, if road conditions are observed to be hazardous, Metrobus customers may experience delays or detours as outlined in Metro’s light snow plan, which adjusts service on a route-by-route basis to keep buses off of steep hills, narrow roadways, and other challenging route segments during inclement weather.

Customers can review planned detours in advance to see how their service may be affected by clicking here. If conditions require that a route be detoured, customers will be notified via MetroAlerts email and text messages. Customers are also encouraged sign up for MetroAlerts and to follow @wmata, @metrobusinfo, and @metrorailinfo on Twitter for the latest service information.

Customers should allow additional travel time and use caution on platforms, escalators, parking lots and other areas that may be slippery.

Elsewhere across the system, Metrorail is expected to operate on a normal weekday schedule. MetroAccess will operate normally, with extra travel time possible based on road conditions.

VDOT is encouraging drivers to stay off the roads after the frozen precipitation starts falling overnight.

Motorists should avoid travel as frozen precipitation will create icy roadway conditions in portions of the Commonwealth tonight and tomorrow morning. Pavement temperatures will be at or near freezing levels. Temperatures will drop overnight and could cause treacherous conditions during the morning commute, primarily in the northern, northwestern and parts of central Virginia. As a reminder, bridges, overpasses and shaded areas tend to freeze first.

Freezing rain is forecasted to begin around 9 p.m. tonight in northwest Virginia and will continue through the morning.

Most Virginia Department of Transportation (VDOT) crews did not apply liquid pretreatment to roads in areas where the event is forecasted to start as rain, as the pretreatment application will wash away and be ineffective. VDOT crews are ready to treat roadways with salt, sand and abrasives once icy conditions begin to develop. Wreckers are pre-staged along certain routes and tree crews are available to handle downed trees.

Motorists should be vigilant, pay attention to weather forecasts in areas where they plan to drive, and delay travel in the impacted areas.

2 Comment
×

Subscribe to our mailing list