Metro’s ‘SafeTrack’ to Start with Single-Tracking Between Ballston and EFC Next Month

Metro SafeTrack plan for June 2016

There will be nearly two weeks of continuous single-tracking between Metro’s Ballston and East Falls Church stations next month, and that’s just the start of a sweeping plan to make Metrorail safer and more reliable.

Metro General Manager Paul Wiedefeld released the final version of its SafeTrack plan on Tuesday. Intended to catch up on years of deferred maintenance, the plan will condense three years of track work into less than a year of a “safety surge,” resulting in major transit disruptions.

SafeTrack logo (image via Metro)The expedited maintenance, which will focus on various high-priority parts of the Metrorail system, comes as a result of the constant track problems and safety concerns about infrastructure Metro has faced over the past year.

The plan extends maintenance times on weekends, weeknights and midday hours and it also contains 15 “safety surge” projects, which will each involve 1-6 weeks of single tracking or complete shutdown of certain parts of the system.

The project will heavily affect rush hour commutes as service on the affected lines will be greatly reduced, resulting in extended wait times and more crowding on trains.

“Safety comes first, and I want to remind the region that SafeTrack is not just about the 15 maintenance surges,” said Wiedefeld in a press release. “SafeTrack also includes weeknight work that will require single track operations in sections starting at 8 p.m.; it means closing the system at midnight on weekends as opposed to 3 a.m. and committing to a moratorium on extra hours of early morning or late night service when it conflicts with track work.”

Here’s the list of track outages will affect Arlington riders:

June 4-16: Ballston to East Falls Church
Impact: Continuous Single Tracking
Service Change: Orange Line runs every 18 minutes to/from stations Vienna to Ballston, additional trains from Ballston to New Carrollton. Silver Line trains run every 18 minutes at all times.

June 18-July 3: Minnesota Ave/Benning Road to Eastern Market
Impact: Entire Line Segment Shutdown
Service Change: Orange and Silver line trains run every 10 minutes at all times, Blue line trains run every 12 minutes between Franconia-Springfield and Arlington Cemetery only. Yellow Rush+ runs all day.

July 5-11: Reagan National Airport to Braddock Road
Impact: Entire Line Segment Shutdown
Service Change: Blue and Yellow line trains run every 12 minutes at all times.

July 12-18: Reagan National Airport to Pentagon City
Impact: Entire Line Segment Shutdown
Service Change: Blue and Yellow line trains run every 12 minutes at all times.

July 20-31: Ballston to East Falls Church
Impact: Continuous Single Tracking
Service Change: Orange Line runs every 18 minutes to/from stations Vienna to Ballston, additional trains from Ballston to New Carrollton. Silver Line trains run every 18 minutes at all times.

Nov. 3-11: East Falls Church to West Falls Church
Impact: Continuous Single Tracking
Service Change: Orange Line trains run every 16 minutes from Vienna to New Carrolton, additional trains from EFC to New Carrollton. Silver Line trains run every 16 minutes.

Dec. 7-24 (Minus Dec. 17): Pentagon to Rosslyn
Impact: Entire Line Shutdown
Service Change: No Blue Line service. Yellow Line Rush+ runs all day, delays and crowding expected. Arlington Cemetery station closed.

Jan. 2-13 and Jan. 23-Feb. 3: Braddock Road to Huntington/Van Dorn St.
Impact: Continuous Single Tracking
Service Change: Blue Line trains run every 18 minutes. Yellow Line trains run every 6 minutes from National Airport to Mt. Vernon Square only. Shuttle trains running between Huntington and King Street only.

March 6-19: East Falls Church to West Falls Church
Impact: Continuous Single Tracking
Service Change: Orange Line trains run every 16 minutes from Vienna to New Carrolton, additional trains from EFC to New Carrollton. Silver Line trains run every 16 minutes.

Recent Stories

Just Reduced includes a 4 BD/3.5 BA home with wooden floors and a floor to ceiling stone fireplace.

As seven-year-old Jaxon Vega positions his skateboard at the top of the concrete bowl at Powhatan Springs Skate Park, he takes a deep breath. Vega steadies the back of the…

A section of Columbia Pike will be reduced to one lane in each direction starting next week. The lane closure, which is set to start Monday and stretch into January…

Clarendon’s newest lash and brow studio is hoping to open next month. A mid-September opening is likely for Deka Lash at 1041 N. Highland Street, a company spokesperson told ARLnow….

Do you struggle with anxiety, depression, stress, grief, trauma or anger? Are
you ready to make a change?

Lauren K. Nickum, LCSW, CSAC from Peaceful Mind Solutions is now taking new
clients for psychotherapy. Lauren has over 10 years of experience treating
mental health disorders and general life stress in adults and adolescents. For
more information visit
peacefulmindsolutions.com.

Submit your own Community Post here.

(This Community Post was written by Signature Theatre and underwritten by Embracing Arlington Arts.)

Signature Theatre just released single tickets for all 33rd season productions, which highlights the organization’s long-time relationship with legendary composer Stephen Sondheim. Beginning with the musical adaptation of The Color Purple and irreverent No Place to Go, the season continues with three Sondheim musicals, the DC premieres of Off-Broadway hit Which Way to the Stage and Pulitzer Prize finalist Selling Kabul, the Tony Award®-winning rock musical Passing Strange, and return of Signature’s cabaret series honoring legendary artists.

“Last November, the world lost an icon. The death of Stephen Sondheim was a blow to everyone in the theater community. Signature Theatre would not be the same without Sondheim — he IS Signature’s ‘signature.’ This season, we are honoring the legend with productions of Into the Woods, Pacific Overtures and Sweeney Todd dedicated to his memory. These shows represent the diversity and range of Sondheim,” said Signature’s Artistic Director Matthew Gardiner about the new season.

Read More

Submit your own Community Post here.

ACFCU’s Homebuying Happy Hour

Are you ready to buy your first home, but concerned about saving for a down payment? Grab a drink and join us for 45 minutes to learn more about how you can buy your first house with 3%, 5%, or

Azure Dream Day Spa Grand Opening

Azure Dream Day Spa is hosting their Grand Opening Celebration at their beautiful new spa located at 901 N. Quincy St. on Friday, August 12 from 5-9 p.m.

All are invited to come tour the new spa and to take

×

Subscribe to our mailing list