New Arlington Homeless Shelter Delayed

2020 14th St. N. (photo via Google Maps)Arlington’s new year-round homeless services center in Courthouse is still another 3-4 months away from completion.

On Saturday the Arlington County Board approved allocating an additional $140,000 to MTFA Architecture, which is providing administration services for the construction project.

County staff said the expenditure is necessary as “a direct result of the construction contractor’s inability to meet its contractual delivery date.”

The shelter was originally expected to be substantially complete by Feb. 27, with final completion 30 days after that.

Miller Brothers, Inc., the contractor, was awarded a $6.6 million contract in Feb. 2014 to convert two-and-a-half floors of offices space at 2020 14th Street N. into a comprehensive facility for serving the county’s homeless population.

The additional funds for the architecture firm will be at least partially offset by a $1,250 per day charge being assessed by the county against Miller Brothers. The county allocated $116,842 plus a $25,000 contingency for MTFA.

“Given the construction delays experienced to date on this project, an additional three (3) months of construction administration, site visits, and support services are anticipated,” according to the staff report. “The requested contingency amount allows for continuing the contractor’s services for another month should there be further construction delays.”

The County Board approved the allocation without public testimony as part of its Consent Agenda.

The new homeless services center will have up to 80 beds and will replace the county’s emergency winter shelter, located two blocks away in Courthouse.