News

Lee and Glebe Intersection Upgrades Underway

The first phase for the upgrades on the intersection between Lee Highway and N. Glebe Road are well underway after construction began March 6.

A spokeswoman for the county’s Dept. of Environmental Services (DES) said the installation of spaces for underground utilities should be done by the end of the year.

After that is complete, utility cables will be transferred underground from the overhead poles. Each individual wooden overhead pole will then be removed and any remaining existing overhead utilities will be rearranged.

Improvements include wider sidewalks, upgraded traffic signals, enhanced left-turn lanes and the installation of left-turn lanes for N. Glebe Road. The area will also get four new bus shelters with real-time arrival information, new streetlights and crosswalk markings.

Currently the construction hours are 9:30 a.m. to 3 p.m. Monday through Thursday and 9:30 a.m. to 2 p.m. on Fridays.

Workers may close a single lane of traffic in one or both directions along Lee Highway, Glebe Road or both during construction. Vehicles turning left or right might also be detoured as construction moves into the intersection itself.

Additionally, some bus stops in the area will be relocated and some sidewalks will be closed or rerouted to allow for construction. Off-street parking in the area may also be reduced in the coming months.

DES says it does not expect any changes to be made to the current design plan for the project.