Traffic

Improvements Underway on S. Walter Reed Drive, With More Changes to Come

S. Walter Reed Drive is slated for several changes that, among other alterations, are designed to make the roadway more pedestrian- and bicycle-friendly.

Construction kicked off last month (July) between 11th Street S. and 13th Street S. That work is scheduled to be completed later this year and primarily targets S. Walter Reed Drive’s intersection with 12th Street S., improving crosswalks and building curb extensions and new ADA-compliant curb ramps.

Also included in the project is the reconstruction of three raised medians to run along that portion of the roadway and alterations to an existing bike boulevard, which will be moved from 12th Street S. to 11th Street S. between S. Highland and S. Cleveland Streets.

Drivers should expect one travel lane to be closed from 9 a.m. to 4 p.m. on weekdays to accommodate construction. Pedestrians will see sidewalk detours and temporary crosswalks, and on-street parking will be restricted.

long-awaited set of changes to a different portion of S. Walter Reed Drive — from S. Arlington Mill Drive to S. Four Mile Run Drive — is set to get underway in mid-September.

That plan has been in the works for years, and the county awarded a $1.8 million contract for it in May. Construction aims to add ADA-compliant bus stops, new crosswalks and curb ramps, more street lighting and improved signals for drivers and pedestrians.

The project also intends to make travel between the Four Mile Run Trail and the Washington & Old Dominion Trail safer and to realign westbound S. Arlington Mill Drive in an effort to make the crossing more accessible to pedestrians and cyclists. The county has been piloting the realignment at the intersection of S. Walter Reed Drive and S. Arlington Mill Drive with a temporary installation since June 2017.

Additional changes to the designated portion of the roadway will include a slight widening of travel lanes and resurfacing.