Join Club

Completion of Fire Station 8 delayed seven months due to permitting delays

Construction on the new Fire Station 8 on Langston Blvd is halfway done but experiencing delays, partly attributed to the county’s own permitting process.

The project at 4845 Langston Blvd, where the old station used to be, is about seven months behind schedule and is now expected to wrap up by January 2024.

Firefighters are operating out of a temporary station at 2217 N. Culpeper Street, just behind the construction site.

This weekend, the Arlington County Board is set to review a request to tack on another $510,000 to its roughly $1.6 million contract with an architecture firm, FGM Architects, to continue providing design and construction administration services.

The total revised budget for the project remains the same, at $27.92 million, given a $2.1 million county-held contingency that’s being used for the overages.

The contractor overseeing construction, MCN Build, agreed to build Fire Station 8 for a guaranteed maximum price of $16,878,504 as the construction manager at risk — meaning it is financially responsible if the project is over-budget.

A staff report says the half-million dollar contract increase is needed for extended construction administrative services because permitting delays have caused the project to fall behind.

Arlington County has transitioned all of its permits online to the Permit Arlington system. Some local home builders previously told ARLnow they are waiting longer for project approval as a result.

Per the staff report, additional administrative and design expertise is also needed to plan for site-related design changes, including realigning a traffic signal, and for inspection and testing services.

“This request… is required for extended construction administrative services to complete the project, including items such as civil coordination with Dominion Energy, Stormwater Pollution Prevention Plan close-out, and other building commissioning support services,” the report says.

Arlington County first used the construction manager at risk model for the Lubber Run Community Center project. Since then it has been used for Jennie Dean Park, which opened nearly a year ago, and the under-construction ART Operations and Maintenance facility.

“This delivery method can better control the project costs and schedule by allowing early builder input on costs, schedule, value, and quality and collaboration with the architect-engineering firm,” the county said in a previous report explaining the terms of the contract with MCN Build.

A more common approach in which a project is fully designed and the contractor with the lowest, responsible bid is awarded the project can result in delayed delivery if, for instance, bids come in over-budget and the whole project has to be redesigned and rebid, the report said.

Involving MCN Build Inc. as design and construction drawings evolved helped those working on the project identify issues early on and address them, the county previously said.

The fire station project has faced other challenges not related to permitting. In February injured workers were rescued by the fire department after their lift made contact with power lines.

Recent Stories

Bronx Pizza is back in Clarendon under a new name: Big Tony’s Pizzeria & Dive Bar. Last May, the pizzeria closed its doors with little warning after doing business for…

It’s likely a hoax but a threatening phone call has prompted another large police response at Yorktown High School.

More than 5,000 Dominion customers were in the dark this morning due to a large power outage.

Arlington Public Schools is pausing an impending middle school boundary process, citing stable enrollment this fall. Earlier this year, APS was bracing for overcrowding at a few middle schools. It…

At Generation Hope, we’re dedicated to supporting teen parents in college as they work toward earning their degrees. We are in need of caring child care volunteers for upcoming events on Saturday, October 21st (in Washington, DC), and Saturday, November 4th (in Arlington, VA). Join our growing volunteer community and support us at an event this fall!

At all of our events, we provide free onsite child care for the children of the teen parents we serve, creating a nurturing environment for the kiddos while their parents learn valuable life skills and build community.

If you enjoy working with children and are looking to make an immediate impact in your community, please visit https://www.generationhope.org/volunteer to learn more.

Submit your own Announcement here.

Join us for Arlington’s biggest civil rights & social justice event of the year. The banquet is back in person at the Arlington Campus of George Mason University.

Our keynote speaker this year is Symone Sanders from MSNBC and former Chief of Staff for Vice-President Kamala Harris.

The Master of Ceremonies is Joshua Cole, former state delegate, NAACP President, and local pastor.

Tickets/seating are limited. Purchase your ticket today! Sponsorship opportunities available.

Read More

Submit your own Announcement here.

The Backyard: After-School Kids Club

Join us at Church of the Covenant on Military Road every other Wednesday afternoon from 4:00-5:30pm beginning on October 18th for The Backyard: After-School Kids Club. Cost is free! The program will provide recreation, snacks, Bible stories, and other fun

Standup Comedy Showcase Starring John F. O’Donnell (Comedy Central)

Live standup comedy starring John F. O’Donnell (Comedy Central)
Friday, October 20

Headliner: John F. O’Donnell

John was a correspondent on the radical comedy news TV show, “Redacted Tonight,” for 5 years. Recently, he released his debut one-hour standup special,

×

Subscribe to our mailing list