Latest design for DCA pedestrian bridge includes more protection from sun and rain

A canopy providing more complete shelter from the elements is included in the latest design proposal for a pedestrian bridge at Reagan National Airport.

Preliminary site development plans for the CC2DCA project include a waterproof canopy over the length of the entire bridge, from its western end at a future Virginia Railway Express station in Crystal City to its eastern end in a lobby at DCA.

The canopy plan is a response to criticisms of conceptual designs released earlier this year, which proposed leaving the bridge open to the sky for aesthetic reasons as it passed over GW Parkway. Such criticisms made up “the great majority of comments” during the most recent public outreach period, according to a project overview scheduled for consideration at the Dec. 3 meeting of the National Capital Planning Commission.

“Many responses indicated that they would not use the bridge during times of inclement weather including high heat, rain, or snow, if it remained uncovered,” meeting materials say. “As a result of public support, the Project incorporated a potential canopy concept in the preliminary design.”

The proposal calls for a lightweight, transparent membrane covering the 958-foot-long bridge, which would cross over GW Parkway and include a 222-foot connection to the Mount Vernon Trail.

Aerial map showing an orange rail route from Crystal City toward the airport, with FUTURE VRE STATION and nearby trails labeled.
Proposed designs for the CC2DCA bridge (via National Capital Planning Commission)

“The bridge alignment was designed to be curvilinear to improve aesthetics and provide as direct a connection as possible to increase user convenience and comfort while reducing impacts to land, existing facilities, and vegetation as much as practicable,” the preliminary submission says.

The project is still in its preliminary design phase, with completion of the 30% design anticipated by the end of 2026. Currently, construction is projected to begin in 2031 and last two years.

“Additional coordination with property owners is anticipated following 30% design to approve the canopy design and determine preferred aesthetics,” the submission says.

Another key consideration for the project: lighting.

The proposal anticipates lighting along “the main spans” of the bridge. At a minimum, the document says, lighting will be included at the connections with the VRE headhouse, the DCA lobby and the intersection with the Mount Vernon Trail.

“In general, the lighting system will be designed for user comfort while minimizing energy cost and impacts to other resources,” staff wrote.

The proposal’s design principles focus on providing a “distinct destination” that prioritizes user experience, is sensitive to the context of the surrounding environment, provides “design clarity” through a consistent aesthetic, and takes an intelligent approach to budget allocation and efficient construction.

About the Author

  • Dan Egitto

    Dan Egitto is the managing editor at ARLnow. Originally from Central Florida, he graduated from Duke University and previously reported at the Palatka Daily News in Florida and the Vallejo Times-Herald in California. Dan joined ARLnow in January 2024.