Around Town

Wilson Blvd Power Station to Get New Facade

Last year, Dominion upgraded the power substation at 3245 Wilson Boulevard to help provide additional power capacity to the ever-developing Clarendon area. As part of the upgrades, Dominion promised a new containment wall that would make the facility easier on the eyes. So far, though, it’s still just a fence.

That has some locals worried. One resident contacted us and pointed out that the Dominion web site lists the project as “complete.” Would the prominently-placed substation remain surrounded by the “ugly” chain link fence?

No, says Dominion spokesperson Le-Ha Anderson. The wall is coming.

“Dominion is working with Arlington County, community members and an art consultant to select a vendor to create the artwork for the façade around the… substation,” Anderson told ARLnow.com. “We expect to have a design proposal by late November – early December.”

Anderson said she expects the wall to be built by spring 2011.