UPDATED: Virginia Kicks in Add’l $65 Million for Pike Streetcar

Columbia Pike streetcar rendering(Updated at 4:40 p.m.) The Commonwealth of Virginia is increasing its funding of the Columbia Pike streetcar system by up to $65 million, Arlington County announced today.

The county says the new funding will enable to Arlington and Fairfax to proceed with the streetcar project more rapidly — accelerating the construction timetable by at least a year — partially thanks to eliminating the need to obtain federal funding.

“The Commonwealth is committed to supporting the Columbia Pike project as a funding partner,” Virginia Transportation Secretary Aubrey Layne said, in a letter to Arlington County Board Chair Jay Fisette and Fairfax County Board of Supervisors Chair Sharon Bulova.

The new funding will also help save $25 million in project costs, according to an Arlington County press release. The Columbia Pike streetcar is now estimated to cost $333 million, about half of which will be funded by the state. The other half of the cost will come from regional transportation funds and local commercial property taxes dedicated to transportation projects.

“No Arlington County homeowner-funded General Obligation bonds will be used to finance design and construction of the streetcar,” the county said.

County Board member Libby Garvey, who along with recently-elected Board member John Vihstadt oppose the streetcar, slammed the state’s decision. Garvey issued the following statement, in which she expresses hope that “the wise voters of Arlington” will vote out Board members who support the streetcar.

I could not be more disappointed in the quick decision by Secretary Layne to devote much needed and scarce transportation dollars to a project as foolish and wasteful as the Columbia Pike streetcar. This project will not improve transit on the Pike. In fact, it will make traffic worse as slow streetcars clog up an already congested thoroughfare. Fortunately, I am pretty sure that within 2 years the wise voters of Arlington will have voted out board members who support the streetcar. That will end the project and allow the Commonwealth, despite this ill advised decision by the Secretary, to spend its money on much more worthwhile and needed projects. I hope that will include a modern and cost effective bus rapid transit system on the Pike in Arlington. That’s what both Arlington and the region need.

Vihstadt also issued a statement, in which has charged that the Commonwealth “rushed to judgment and failed to perform the independent due diligence expected of a state agency to fully analyze this ill-advised local government request.”

“Many valuable transportation projects for which there is a broad public consensus, ranging from improved Metro and bus service to road and pedestrian safety enhancements, will be sacrificed for this controversial project that has deeply divided Arlington County and contributed heavily to my election on April 8 as the first non-Democrat to the County Board since 1999,” Vihstadt said.

The county’s press release, after the jump.

Virginia Transportation Secretary Aubrey Layne has notified Arlington and Fairfax County officials that the Commonwealth will increase its funding for the Columbia Pike streetcar by up to $65 million, using new funding available for fixed-guideway projects. The new funding will bring the state’s contribution to the Columbia Pike streetcar to as much as 50 percent of total design and construction costs.

“The Commonwealth is committed to supporting the Columbia Pike project as a funding partner,” Layne said in his July 10 letter to Arlington County Board Chair Jay Fisette and Fairfax County Board of Supervisors Chairman Sharon Bulova.

The State’s commitment enables Arlington to put together a financial package for the project that does not include Federal Transportation Administration New Starts funding.

Arlington and Fairfax Counties are partners in the planned Columbia Pike streetcar, which will stretch 4.9 miles from the Skyline area of Fairfax to Pentagon City in Arlington along the most heavily traveled bus corridor in the Commonwealth. The Columbia Pike streetcar, one of two segments in Arlington’s planned 7.4-mile seamless streetcar system, will support the community’s vision of transforming the Pike into a more transit-oriented, walkable Main Street.

Arlington County Board Chair Jay Fisette and Fairfax County Board of Supervisors chairman Sharon Bulova wrote to Layne in June, asking that the Commonwealth consider funding the Columbia Pike streetcar project.

“This additional state funding is great news for the streetcar,” Fisette said Friday. “It is both a strong vote of confidence that the streetcar is a transit investment that will benefit the entire Commonwealth, and brings funding certainty that significantly boosts our efforts to build the Columbia Pike segment more quickly, at reduced cost.”

The state’s total contribution to the project, which will include standard transit reimbursement funding, is expected to account for up to half of the streetcar’s design and construction costs. The new grant will be split between Arlington and Fairfax, with Arlington receiving $52 million and Fairfax receiving $13 million.

“The state is making a sound transportation investment by increasing its funding for the Columbia Pike streetcar,” said Bulova. “This funding will help this important transit project get built more quickly, at a lower cost, and will help transform one of the region’s most important corridors.”

In his letter, Layne noted that “the Columbia Pike corridor currently has the highest transit ridership within the Commonwealth for a corridor without fixed-guideway service.” The streetcar project, he wrote, “provides a sound example of leveraging transportation investment to enhance economic competitiveness and provide access for residents of the DC metropolitan area to reach employment opportunities in Virginia.”

Allows project to advance more rapidly

Arlington estimates that the increased state funding will shave at least a year off the construction time for the project, allowing both jurisdictions to more quickly realize a return on investment from the streetcar. The time savings, combined with a lower escalation rate, would save an estimated $25 million.

In June, Arlington signed a contract with Parsons Transportation Group to help manage the entire streetcar program. In the coming months, one of Parsons’ primary tasks will be to assess options for cost reduction by analyzing ways to deliver the streetcar sooner. This could include combining final design and construction work in a single contract or exploring potential public-private partnerships.

The latest estimated cost to build the Columbia Pike streetcar is $333 million. With the new state grant, the County Manager will recommend that Arlington cover the rest of its share through a combination of new regional transportation funding and local commercial real estate tax revenues dedicated by law solely to new transportation projects. No Arlington County homeowner-funded General Obligation bonds will be used to finance design and construction of the streetcar.

After a lengthy public process, the Arlington County Board is expected to adopt its Capital Improvement Plan, which will include the latest cost and schedule estimates for the streetcar, on July 19.

Arlington’s streetcar system

Arlington’s planned streetcar system includes the Columbia Pike segment and the Crystal City-Potomac Yard segment. The two segments will intersect at Pentagon City, where the streetcar will also connect with the regional transportation system – both Metrorail and Virginia Railway Express (VRE). The streetcars will operate along with buses to serve the growth in jobs and population expected along these corridors.

Streetcar expected to generate up to $895 million in new local tax revenues

The Columbia Pike streetcar segment, based on a study released in March, is expected to generate a substantial economic and fiscal return. The study estimated that the streetcar will generate $3.2 billion to $4.4 billion in new real estate value for Arlington and Fairfax Counties over 30 years. That is over and above project capital and operating costs. The streetcar investment is also projected to generate $455-$895 million in new tax revenues for Arlington and Fairfax over a 30-year period, attract 6,600 new jobs to the corridor within 10 years of project construction and increase state income and sales taxes.

Next steps

The two Counties now will work with the Department of Rail and Public Transportation (DRPT) to put together a milestone schedule that would outline the steps needed to move the project forward and execute a grant agreement with the state that will address the final amount and timing of the funding.

Recent Stories

Good Thursday evening, Arlington. Let’s take a look back at today’s stories and a look forward to tomorrow’s event calendar. 🕗 News recap The following articles were published earlier today…

Last year, an attempt to broaden the Arlington police auditor’s access to police records quietly fizzled before reaching the public for discussion.

George Mason University’s new Fuse at Mason Square in Arlington, is poised to become a 345,000-square-foot collaborative and digital innovation space in the heart of the Rosslyn-Ballston Corridor. “As Mason expands in…

These tree care companies serve Arlington County and received Washington Consumers’ Checkbook’s top rating for quality (as reported by their customers in Checkbook’s surveys).

Award-winning drag queen Tara Hoot is bringing her Family Fun Story Time Brunch to Arlington at Freddie’s Beach Bar! Saturday April 6 at noon! Join Tara for songs, stories, puppets, bubbles and joy! It’s not just stories, it’s a SHOW that’s perfect for kids and kids at heart–fun for everyone! Plus a tasty brunch at Freddie’s! Click the link and make your reservations now! ❤️ 🫧 🌈

Submit your own Announcement here.

The Summer 2024 STEAM (Science/Technology/Engineering/Arts/Math) Fellowship application is now open! Apply by April 15 to be considered!

The STEAM Workforce Development Teacher Fellowship provides Arlington Public Schools (APS) high school, middle school, and elementary school teachers with opportunities to learn about workplace needs in STEAM-related fields and for them to use the experience to enhance student learning to match workplace expectations in a selected industry. STEAM Fellows participate in a three-week summer fellowship, receiving a $4,000 stipend upon completion.

Applicants planning to pursue a fellowship in the arts must demonstrate how they will build connections between the arts and science, technology, engineering, or mathematics.

Click the button to learn more, share, apply, and see the variety of fellowships completed in previous years.

Read More

Submit your own Announcement here.

Free Right-Sizing Workshop – How to Get Rid of Your…

Cody Chance and Dick Nathan of Long & Foster are hosting a free workshop at our office on Cherry Hill Rd. (formerly Lee Highway) on the topic of “down-sizing” Thursday, March 28 from 5:30-7:30. We have created a workbook with

Portofino Italian Wine Dinner, April 6, 6:30pm

Four course Italian dinner, paired with 2 wines each. The wines will be served “blind” and notes on each wine will be discussed. The event is coordinated with Elite Wine Importers and The Portofino Restaurant. The dinner is on Saturday,

×

Subscribe to our mailing list