(Updated at 4:35 p.m.) Metro has released its final version of the SafeTrack plan, beginning with work between the East Falls Church and Ballston stations.

This morning Metro General Manager Paul Wiedefeld outlined the agency’s plan for working through Metrorail’s deferred maintenance backlog.

The “safety surge,” dubbed SafeTrack, “accomplishes in one year, work that otherwise would take about three years to complete.” It comes at a time when major Metro track problems and electrical fires seem to be increasingly commonplace.

The plan involves fifteen long-duration track outages between June 4 and May 8, 2017, to allow for extensive track work.

The goal: to achieve “safety and state of good repair of basic track structure.”

So what can Arlington riders expect? First, there will be a moratorium on early system openings and closings — the system will close at midnight, seven day a week.

Additionally, the following track outages are planned.

Metro SafeTrack logoJuly 5-12
National Airport to Braddock Road

Impact: Entire line segment shut down
Service Reduction: Trains running every 12 minutes at Virginia Blue and Yellow Line stations

July 12-19
National Airport to Pentagon City
Impact: Entire line segment shut down
Service Reduction: Trains running every 12 minutes at Virginia Blue and Yellow Line stations

Aug. 20-Sept. 6
Eastern Market to Minnesota Ave/Benning Road 
Impact: Entire line segment shut down
Service Reductions: Three lines affected. Orange and Silver lines running every 10 minutes, Blue Line running every 12 minutes.

Nov. 2-12
West Falls Church to East Falls Church
Impact: Continuous single tracking
Service Reduction: Trains on Orange and Silver lines each running every 16 minutes

Nov. 12-Dec. 5
East Falls Church to Ballston
Impact: Continuous single tracking
Service Reduction: Trains on Silver Line running every 18 minutes, Orange Line trains from Vienna to Ballston running every 18 minutes

Dec. 6-24
Pentagon to Rossyln
Impact: Entire line segment shut down, Arlington Cemetery station closed
Service Reduction: Reduced service at all Blue Line stations

March 6-14
West Falls Church to East Falls Church
Impact: Continuous single tracking
Service Reduction: Trains on Orange and Silver lines each running every 16 minutes

April 16-May 8
Braddock Road to Huntington/Van Dorn 
Impact: Continuous single tracking
Service Reduction: Trains on Blue Line running every 18 minutes

In order to maximize productivity, all of the track outages will be continuous and will affect rush hour service. For the line segment shut downs, buses will replace trains around the station closures.

The safety surge will not only affect Metro riders, it’s expected to affect those who drive as well, in the form of additional traffic.

Here’s what Rep. Don Beyer (D-Va.) had to say about the plan.

After the jump, the full press release from Metro.

Metro General Manager/CEO Paul J. Wiedefeld today released SafeTrack, an expanded track work plan to improve Metrorail safety and restore service reliability.

Wiedefeld’s SafeTrack plan includes 15 “safety surges” over the next year that will accelerate maintenance on Metro’s rail system from the ballast up. By closing the system at midnight on weekends and expanding weekday maintenance opportunities, the plan addresses FTA and NTSB safety recommendations and deferred maintenance backlogs while restoring track infrastructure to good health.

SafeTrack accomplishes in one year, work that otherwise would take about three years to complete.

Fifteen “safety surges” are planned that will allow track crews to exponentially increase productivity and achieve safety results for customers faster. These long-duration track outages use either around-the-clock single tracking or line-segment shutdowns that will impact rush hour commutes. Metrorail riders will be encouraged to consider using alternate travel options while safety surge work is in effect on their line.

In addition, Wiedefeld announced a moratorium on early openings and late closings. Closure of the Metrorail system at midnight seven days a week will begin Friday, June 3.

“This plan is going to take some sacrifice from all of us,” Wiedefeld said. “But it is clear that the current approach is not working, more aggressive action is necessary.”

Following the review and consideration of traffic mitigation and alternate travel options by the Department of Transportation (DOT) agencies in the District of Columbia, Maryland and Virginia, regional law enforcement, Office of Personnel Management (OPM), Department of Homeland Security and General Services Administration (GSA), a final version of SafeTrack will be released for riders on May 16.

“Metro’s safety culture change depends on support from the entire region,” said Wiedefeld. “We have to begin by understanding that safety trumps inconvenience.”

Recent Stories

Memorial Day is a special time to remember and show appreciation for the courageous men and women who sacrificed their lives for our country. It’s also an opportunity to come…

Good Friday evening, Arlington. Today we published articles that were read a total of 8149 times… so far. 📈 Top stories The following are the most-read articles for today —…

It’s Memorial Day weekend in Arlington. The flags are in at Arlington National Cemetery, ‘Rolling to Remember’ participants are rolling up to local hotels, and the 35% of locals who…

(Updated at 2:45 p.m.) Today is the first day high school-aged Arlington Public Schools students can carry naloxone in schools. Students in grades 9 and above can now carry the…

36TH FESTIVAL ARGENTINO

ARLINGTON JUNE 3RD, 2023

Sat, June 3rd I 3:30 pm / Shows 5:50 pm I Kenmore Auditorium I Glencarlyn

The 36th Festival Argentino USA celebrates Argentine Day and Cultural Freedom. The folkloric group Los 4 de Córdoba and 25 more artists from Argentina, World, and Solidarity Tribute, 200 years of friendship between USA and Argentina!.

Read More

Submit your own Announcement here.

We have an exciting Juneteenth program with speakers sharing historic artifacts that tell the rich history of Arlington’s Black community builders. 

Friday, June 16, 2023

7:00 – 8:00 pm

Arlington Historical Museum

Read More

Submit your own Announcement here.

Homebuying 101: Steps to Getting Pre-Approved

Are you ready to jump into homeownership or started considering it but don’t know where to start? Financial preparation is key when thinking about purchasing your first home and the first step to getting pre-approved.

Join ACFCU’s mortgage loan officers

4th of July Celebration & Fireworks

Treat yourself this Independence Day with a world-class, private 4th of July extravaganza at the Military Women’s Memorial – a premier National Capital Region site.

Great food, fun, and the best views of Washington DC’s spectacular fireworks display. Relax, enjoy,

×

Subscribe to our mailing list