Around Town

Custis Trail Detours Begin Wednesday in Rosslyn

Custis Trail detours through Rosslyn (Courtesy Arlington County)Users of the Custis Trail around Rosslyn will begin experiencing phased detours starting tomorrow, as crews start utility work nearby.

From tomorrow until April 17, the trail will be rerouted east of N. Lynn Street onto an adjacent paved public driveway, according to Arlington County.

The route will have a steeper grade than the current trail, so bicyclists are advised to dismount before entering the detour zone.

On April 18, the next phase sees the trail rerouted at the northeast corner of its crossing at N. Lynn Street. The crossing will be shifted north until May 8.

The fourth and final phase begins May 9 west of N. Lynn Street, with the trail rerouted to the south side of Lee Highway between N. Lynn Street and N. Fort Myer Drive by Gateway Park until June 1. As the detour route for this phase is narrower than the current trail, bicyclists are asked to dismount or slow down when pedestrians are nearby.

Workers from the county along with the Virginia Department of Transportation and Dominion Virginia Power will be performing the work as part of the Lynn Street Esplanade & Custis Trail Improvements project. The project is intended to improve safety for bicyclists and pedestrians, particularly at the dangerous intersection of Lynn Street and Lee Highway.

Signs will inform trail users of the various detours, and work dates may vary.