Yorktown High School Modifications Set For Approval

The final design of Yorktown High School modifications that will increase the building’s capacity to 2,189 seats is set to be approved at the Arlington School Board meeting on Thursday (March 8).

Per the plan, at least six classrooms will be created by converting a computer lab, a computer alcove, and several teacher work rooms. A copy room will turn into a new “teacher collaboration space,” and other teacher work space and offices will also be reconfigured.

Existing storage will be turned into bicycle storage, and charging stations will be added throughout the school, including in the cafeteria and atrium. The current gym lockers will be replaced.

The larger seating capacity comes weeks after the proposed Arlington Public Schools budget was announced with class size increases.

The project’s estimated $4 million cost will be funded by the capital reserve, according to School Board documents.