Traffic

VDOT will close the lane as soon as tomorrow as part of the ongoing Washington Boulevard bridge and interchange project. Drivers should expect new traffic patterns on eastbound Columbia Pike as a result.

“Motorists in the right lane must take the exit ramp to Washington Boulevard,” VDOT said in a press release. “Motorists on eastbound Columbia Pike can use the left lane to continue east or to access the ramp to Washington Boulevard.”


Traffic

The three year, $51.5 million project will ultimately result in the construction of a new, wider Washington Boulevard bridge over Columbia Pike, complete with a reconfigured ramps, additional bridge clearance and a new shared use path along Columbia Pike. To help facilitate the construction, daily lane closures on Washington Boulevard will start this week.

“Drivers can expect single lane closures daily on Washington Boulevard in both directions from 9 a.m. until 3 p.m.,” VDOT said in a press release. “Drivers can also expect periodic traffic shifts, the first this summer to new temporary pavement crews will construct over the next few months.”


News

The project has been about two decades in the making, and VDOT spokeswoman Joan Morris says it finally got underway this week. Right now, it’s still in the very preliminary stages while workers set up a field office and work out logistics.

The revamp is supposed to have eight stages, and is slated to run through August 2015. Once the first stage gains steam, a detour will be constructed for use on certain weekends. VDOT says traffic may need to be re-routed during off-peak hours, but efforts will be made to keep lanes clear during the morning and evening rush hours on weekdays.


Traffic

Starting this spring — as soon as final regulatory approvals are issued — crews will begin work on the first of eight construction phases that will stretch through August 2015. During that first phase, a detour will be constructed, using the north interchange ramps to provide a signalized, at-grade intersection on Washington Boulevard.

That detour is expected to be used for 3 to 5 weekends per year, starting this summer, when crews need to shut down Columbia Pike for demolition of the existing Washington Boulevard bridge and construction of a pair of new spans, just east of the existing bridge. The detour will also include facilities for pedestrians.


News

At a community meeting on Tuesday, VDOT project manager Christiana Briganti-Dunn said land acquisition and construction is expected to begin this spring and will be complete by Aug. 2015. The $51.5 million project is being paid for primarily with federal and state funds, although Arlington is expected to contribute about $1 million for utility relocation and upgrades.

The project will replace the crumbling Washington Boulevard bridge, which dates back to the 1940s, and replace it with a new, wider span that will be dubbed the Freedman’s Village Bridge, in honor of the enclave of freed slaves that was established nearby in 1863 and remained until the 1890s.


News

The good news is that both thoroughfares will remain open during construction of the new Washington Boulevard bridge, a three-year process that’s expected to begin next fall. Plus, all original travel lanes on each will be open during rush hour and during certain special events and federal holidays.

The bad news is that during the day, during construction, the re-routing of Columbia Pike traffic around the bridge may get a bit funky and cause some delays. The contractor selected to undertake the project will ultimately be able to design their own traffic management scheme, but the plan initially envisioned by VDOT involves directing Columbia Pike traffic up the existing ramps to a makeshift stop light on Washington Boulevard, turning Washington Boulevard and Columbia Pike into a four-way intersection.