DEVELOPING: Long Bridge Aquatics Center on Hold Due to Rising Costs

Renderings of the future Long Bridge Park Aquatics, Health & Fitness FacilityConstruction of the Long Bridge Park Aquatics, Health and Fitness Facility is on hold due to higher-than-expected construction costs.

Arlington County Manager Barbara Donnellan announced late Friday afternoon that construction bids for the first phase of the Long Bridge Park aquatics center came in “significantly higher” than the $79.3 million projected cost. As a result, Donnellan says she will not be recommending a construction contract for County Board approval in early 2014, as planned.

Donnellan said it was “disappointing” that the bids far exceeded the estimate provided by its architect, which was in turn backed up by a third-party firm.

“The high bids were particularly disappointing because the County had done extensive due diligence to ensure that the estimate was sound and within the available budget,” she said in a statement. “We took an additional step of contracting separately with an engineering firm to review design and construction documents and provide independent third party cost estimates.”

Renderings of the future Long Bridge Park Aquatics, Health & Fitness Facility“Once staff concludes its assessment of the bids and our architects’ estimates, I will present options to the County Board for next steps,” she continued. “In the months ahead, the County Board and the community will continue their careful consideration of the costs and benefits of building and operating this facility as we shape the FY 2015 Budget and the Capital Improvement Program.”

Reached by phone Friday evening, Donnellan told ARLnow.com that she expects to receive recommendations from county staff as early as February. She declined to speculate about the recommendation, saying that there’s significant work and analysis left to be done by staff.

Donnellan also declined to specify how many bids were received and how much higher those bids were than the estimate, citing legal constraints.

News of the delay in the project comes just a month after news that the aquatics center’s operating deficit would be 2 to 4 times that of original estimates. Local fiscal watchdog Wayne Kubicki says the county should consider scrapping the project altogether.

Renderings of the future Long Bridge Park Aquatics, Health & Fitness Facility“This project has been mishandled by the County Board almost from the beginning,” he said. “With the pressures on other parts of the county and school budgets and the stagnation of commercial real estate values, it might well be time to moth ball the Long Bridge aquatics facility and simply leave the current park as-is.”

At least two candidates for the upcoming County Board special election — John Vihstadt and Evan Bernick — are on record as saying they oppose the aquatics center project.

Construction bids received by the county for the project were technically for “Phase 2” of Long Bridge Park, which encompasses both the initial phase of the aquatics center and minor improvements to the park itself, including “public gathering areas, trails, public art, interpretive signs, and walkways.” Much of the funding for the projected cost of Phase 2 has already been secured, including $42.5 million from a parks bond approved in 2012 and $15 million from Vornado as part of the PenPlace development.

Renderings of the future Long Bridge Park Aquatics, Health & Fitness FacilityA Phase 3A and 3B, for other park improvements, are also planned, as is a Phase 4, which would complete the Aquatics, Health & Fitness Facility by adding a large “multiple activity center,” additional fitness space, racquetball and squash courts, a climbing wall, an elevated jogging trail, rental meeting rooms and a 547-space underground parking garage.

“Long Bridge Park is an ambitious project for our community, an infrastructure investment that is transforming a one-time industrial wasteland from a brownfield to an iconic gateway on the Potomac,” Donnellan said in her statement. “It will provide multiple recreational opportunities for our growing population and for future generations.”

Recent Stories

Daily Debrief for Nov 30, 2022

Good Wednesday evening, Arlington. Today we published 5 articles that were read a total of 12854 times… so far. 📈 Top stories The following are the most-read articles for today…

Arlington’s fire and police unions are poised to lose a battle to change the pay scale the county uses — one that union representatives say contributes to ongoing staffing shortages….

Shop Local Winter Bazaar

Shop local this holiday season at the Winter Bazaar taking place Saturday, December 17-18.

(Updated at 10:20 p.m.) It does not appear that the Asian-inspired restaurant Wagamama will be opening in Clarendon this year. Back in March, the London-based chain with more than 200…

Grab some friends and sign up for Parks & Rec’s Eugene J. Green Memorial Winter Basketball League! Adults 18+ can register teams of up to 12 people for the ten-game season. Cost is $765 per team. Games are Mondays and/or Wednesdays at Arlington Mill Community Center starting the week of Jan. 4. Sign up here by Dec. 11.

Submit your own Announcement here.

National Chamber Ensemble – Holiday Cheer!

NCE’s Holiday Concert will bring the finest classical masterpieces and holiday favorites together for the whole family. The festivities begin with Leroy Anderson’s classic “Sleigh Ride” and “Chanukkah Festival”, music from the Nutcracker and by J.S. Bach.

Outstanding Young Artist

Washington-Liberty Annual Holiday Bazaar

Join us Saturday December 3 from 10 to 4 p.m. at W-L High School, for this much anticipated Arlington holiday tradition! We will be featuring over 65 vendors for gift shopping, our student clubs and activities fundraising booths, and food

×

Subscribe to our mailing list