The following was sent in response to last week’s letter to the editor, “The Case for Long Bridge Park Phase 2.”

I am an Arlington resident and have been for 15 years. I would like to respond to Eric Cassel, President Friends of Long Bridge Park. First he makes the case that the target audience for this lavish facility is increasing in Arlington County. Target audience? Elementary school age children — I have lived in six states while I was growing up. In not one state was there a swimming facility for us to learn how to swim. How did this become a necessity for elementary school children? At what point did “we” decide that my elementary schooling when I was a child was lacking?


Opinion

The Right Note is a weekly opinion column published on Thursdays. The views and opinions expressed in the column are those of the author and do not necessarily reflect the views of ARLnow.com.

As it turns out, that still may not be enough. County Manager Barbara Donnellan had to halt forward progress on the new facility when bids came in well over the already-generous cost estimates. This was on top of the recent announcement that annual taxpayer subsidies for the ongoing operational costs of the project were ballooning dramatically over the original cost estimates. The new estimate is that the aquatics center will operate at a deficit of $4 million per year.


Opinion

Peter’s Take is a weekly opinion column. The views and opinions expressed in this column are those of the author and do not necessarily reflect the views of ARLnow.com.

On Dec. 12, I recommended that the County Board direct the County Manager to “halt all further work on the Aquatics Center… and develop a new, cost-effective design for a sensible recreation center at Long Bridge Park (including a swimming pool).” Little did I know when I wrote that December column that the construction bids to build this facility also would come in so much higher than anticipated.


News

Arlington County Manager Barbara Donnellan announced late Friday afternoon that construction bids for the first phase of the Long Bridge Park aquatics center came in “significantly higher” than the $79.3 million projected cost. As a result, Donnellan says she will not be recommending a construction contract for County Board approval in early 2014, as planned.

Donnellan said it was “disappointing” that the bids far exceeded the estimate provided by its architect, which was in turn backed up by a third-party firm.


News

Garvey is endorsing self-identified Republican John Vihstadt, who announced last week that he would run as an independent in the spring 2014 special election.

Garvey stated that none of the three announced Democratic candidates likely will change the way the current Board members set priorities. She decided to endorse Vihstadt instead because she believes he can provide change.


Opinion

Peter’s Take is a weekly opinion column. The views and opinions expressed in this column are those of the author and do not necessarily reflect the views of ARLnow.com.

The Aquatics Center hasn’t been built yet, and it shouldn’t be built. The County Board should scrap its Olympian pretensions and its desire to build King’s Dominion North at the expense of Arlington taxpayers. The board should explain its decision as follows: “We have made a mistake, and we are going to fix it. We have new information, and we are going to act on it.”


News

The aquatics center, scheduled to open in the summer of 2016, had been projected to have an annual operating deficit of $1 million to $1.3 million. That number has been upped to $4.3 million. But Department of Parks and Recreation Director Jane Rudolph said in a statement that comparing those numbers is not comparing “apples to apples.”

Rudolph explained that the original numbers published in the 2012 Capital Improvement Plan were in “2012 numbers,” whereas the new estimate is adjusted for inflation with “2020 numbers.” The statement reads, in part, “The 2012 tax support number — of $1.1 to $1.4 million if presented at a 2020 level would range from $1.4 million to $1.9 million. The 2020 tax support number presented in the November 2013 revenue and expense forecast ($4.3 million) was at the maximum of the range (as it should have been). The apples to apples increase in estimates is $2.4 million.”


News

Projected Subsidy Soars for Aquatics Center — The planned Long Bridge Park Aquatics Center could require more than $4 million per year in subsidies from the county government, according to new projections. That’s up from projections as low at $1 million per year. “Certainly there are other priorities that arguably should come before building a luxury pools facility,” said local fiscal watchdog Wayne Kubicki. Construction contracts for the aquatics center are expected to be awarded early next year. [Sun Gazette]

County May Allow Less Office Parking, For a Fee — Arlington County is considering a system that would allow office developers to build less than the currently-required amount of parking, in exchange for a per-parking-space fee. The fee would then be used for public improvements in the area around the building, or for Transportation Demand Management Services for the building’s tenants. [Greater Greater Washington]


News

Work on the approximately $80 million facility, located just north of Crystal City near I-395, is now not expected to begin until early 2014, according to Arlington Department of Parks and Recreation spokeswoman Susan Kalish.

“To ensure that we have quality general contractors bidding… we decided to undertake an extensive pre-qualification process,” Kalish explained. “That process is now complete and we have our selected pool of contractors. The bidding process will take place over the next several months. We anticipate that construction will begin in early 2014.”


News

It was announced in June that a company had submitted an unsolicited proposal to transform Alexandria’s Hensley Park into a sports and entertainment facility. The proposed complex included features like an Olympic-sized pool and water play area; basketball, volleyball, baseball and gymnastics centers; ice rinks; indoor tennis and squash courts; a climbing wall; and a driving range.

A pool, water play area, climbing wall and racquetball courts are all also part of Arlington’s plan for the Long Bridge Park facility. (County Board Chair Walter Tejada said in June that he did not expect the Alexandria proposal to impact the county’s plans.)


News

The Alexandria City Council discussed the proposal it received from The St. James Group LLC during its meeting on Tuesday. The plan involves a long term lease of the 15 acre city owned property currently occupied by Hensley Park.

The Alexandria proposal includes amenities such as an Olympic sized pool and water play area, climbing wall and racquetball courts. Those features had already been included in Arlington’s long term plan for Long Bridge Park.