News

Classrooms, Police Cars and More Proposed for ‘Buck Site’

The “Buck Site” — a county-owned property across N. Quincy Street from Washington-Lee High School — could serve a smörgåsbord of Arlington’s needs.

Last week the Joint Facilities Advisory Commission (JFAC) reviewed proposed uses for four building renovations planned for the site to fit needs across several local departments and Arlington Public Schools (APS).

According to the Phase 3 plans, the Buck 1 building closest to N. Quincy Street would be used as a logistics hub for the Arlington County Fire Department.

Buck 3, a building farther back in the site, would be used for police storage.

According to Jessica Baxter, a spokeswoman for Arlington County’s Department of Environmental Services, the county is moving forward with renovations to the warehouse building at 1425 N. Quincy Street to accommodate the relocation of police reserve vehicles.

The police vehicles are being relocated due to the upcoming construction at Jennie Dean Park near Shirlington, where they’re currently stored.

The planned use for the two other buildings at the site is still to be determined. Baxter said the county is waiting to hear what the top priority would be from APS.

“The two office buildings at 1429 and 1439 N. Quincy Street (Buck 2 and 4) are being considered for instructional space and/or the relocation of APS’s administrative offices, trade shops, and associated white fleet vehicles from the Trades Center in Shirlington, for APS’s growing needs,” Baxter wrote. “APS will decide whether to proceed with the uses of these buildings, and is to let the county know this fall.”

Last June, the County Board approved an agreement that would allow APS to park vehicles at the property.

If APS does not proceed with classrooms or an administrative use in those buildings, the county’s plans are to convert Buck 2 into county offices and a facility for Public Safety Communications and Emergency Management (PSCEM).

The presentation at the JFAC meeting also included estimated renovation costs for each of the buildings:

  • Buck 1 (Fire logistics) — $8 million-$10 million
  • Buck 2 (APS classrooms or county offices) — $14.5 million-$20 million
  • Buck 3 (Police vehicle and equipment storage) — $7 million-$9 million
  • Buck 4 (APS classrooms, administrative, or PSCEM) — $14 million-$24 million
  • General site renovations — $4 million

An alternative design for the site, also under consideration, envisions the Buck Site as a recreational field, multi-use athletic field and youth/rec baseball field was also presented at the meeting, with a $13.5 million cost estimate.

Photo via Google Maps