VDOT Planning Closures On I-66 Next Week

It won’t be nearly as disruptive as the year-long, round-the-clock lane closures on Columbia Pike, but VDOT is planning temporary closures on I-66 next week.

One lane of eastbound I-66 will be closed nightly — from 9:30 p.m. to 5 a.m. — in the East Falls Church area on Monday and Tuesday, the state transportation agency said. There will also be multiple, brief closures of Sycamore Street and eastbound I-66 during that time.

The closure will allow the installation of bridge girders as part of the project to add a lane to eastbound I-66 between the Dulles Connector Road and Ballston.

More from a VDOT press release:

Bridge girder installation to widen I-66 East will require multiple brief closures of Sycamore Street in Arlington during overnight hours on January 6 and 7. Additionally, the left lane of I-66 East will be closed while crews install six bridge girders as part of the I-66 Eastbound Widening Project.

Details:

  • The left lane of I-66 East will be closed from 9:30 p.m. to 5 a.m. on the nights of Monday, Jan. 6, and Tuesday, Jan. 7.
  • There will be a full 20-minute closure of I-66 East shortly after midnight the night of Monday, Jan. 6, so that girders can be delivered to the work area.
  • Vehicle and pedestrian traffic on Sycamore Street under I-66 will be stopped for up to 20 minutes at a time between midnight and 4 a.m. multiple times each night. Stoppages are planned for northbound traffic on the first night, then southbound traffic the second night.
  • Pedestrians will be directed to the opposite sidewalk to proceed through the work zone.

All work is weather dependent.

Drivers and pedestrians are urged to use caution and expect possible delays. Real-time traffic conditions and information is available at www.511virginia.org or through the 511 Virginia mobile app.

The I-66 Eastbound Widening Project will add a travel lane along four miles of eastbound I-66 and install approximately 12,000 linear feet of new and replacement noise barriers. The project also includes building a new bridge over Lee Highway (Route 29) for the Washington & Old Dominion (W&OD) Trail, and constructing a new direct access ramp from eastbound I-66 to the West Falls Church Metrorail Station at the Route 7 Interchange.

The additional eastbound lane is scheduled to open to traffic in fall 2020, and the overall project is expected to be complete in fall 2021. Learn more about the I-66 Eastbound Widening Project and sign up for project updates and lane closure alerts at Transform66.org.