VDOT to repair 50-year-old bridge over I-395 near Shirlington next year

A 50-year-old bridge over I-395 near Shirlington is slated for upgrades next year.

Locals can learn more about the planned bridge work next Tuesday evening during a virtual meeting hosted by VDOT, which is managing the project.

The bridge connects the southbound I-395 collector-distributor lanes and southbound Shirlington Road to N. Quaker Lane at the I-395 Exit 6 interchange.

First constructed in 1973, the bridge needs upgrades to improve safety for drivers and to extend its usable lifespan, says VDOT. Today, the bridge is crossed by about 7,400 vehicles daily.

The bridge over I-395 in Shirlington slated for repairs (via Google Maps) 

According to the project webpage, VDOT will:

  • Resurface the concrete bridge deck and closing deck joints
  • Repair concrete piers and abutments
  • Repair and repaint steel beams
  • Add protective concrete barriers adjacent to piers
  • Replace bearings
  • Upgrade guardrails adjacent to the bridge

The $4.3-million project will be financed with federal and state funding, including State of Good Repair funds used for bridges.

Next Tuesday’s meeting will begin at 7 p.m. VDOT staff will make a short presentation and then answer questions from the public for an hour. Project materials, which are not yet available, will be posted on the meeting webpage before the meeting starts, the department says.

Through Friday, March 25, VDOT will accept feedback via email and U.S. mail, addressed to Vicente Valeza, Jr., P.E., Virginia Department of Transportation, 4975 Alliance Drive, Fairfax, VA 22030.