News

New Seating, Bus Bays Coming to Ballston Metro Station Entrance

The Arlington County Board has approved a nearly $5.5 million contract to revamp the area around the Ballston Metro station.

The project — a refinement of an earlier plan, which we last reported in 2014 — will build nine bus bays, covered bus shelters and new seating areas.

More from Arlington County:

The Board voted unanimously to approve a $5.45 million contract, including $909,080 (20 percent) contingency, with Ardent Company, LLC for major improvements to the bus stop and seating areas along North Fairfax Drive and North Stuart Street. The project will expand pedestrian circulation spaces, and add real-time information displays to nine bus stops in the area. Antiquated streetlights will be upgraded, landscaping added and the existing bus driveway on Fairfax Drive will be replaced with four new saw-tooth bus bays. The North Stuart Street sidewalk will be made more accessible to persons with disabilities.

The project, included in the County’s Capital Improvement Plan, will be funded with a combination of federal, state and local funds. It is expected to begin in early spring 2020 and last for 18 months.

“Upon completion, Arlington County will take ownership and maintenance responsibility of the new furniture, information signage, and bus shelters,” a county staff report notes.

“As Arlington grows, it is essential that the County continue to improve our transportation infrastructure,” County Board Chair Christian Dorsey said in a statement.

A separate plan calls for the Ballston Metro canopy to be replaced with a public art installation, “which will consist of a dozens of LEDs that can be individually programmed to respond to motion sensors that detect riders coming in and out of the station.”

The county is also currently working to kickstart a project to build a second entrance to the Ballston Metro entrance.

Photo via Google Maps