Plans for Crystal City Metro second entrance changed to lower costs

(Updated at 3:05 p.m.) Arlington County and JBG Smith are changing up plans for a second entrance to the Crystal City Metro station due to projected cost overruns.

An east entrance to the station — a long-standing goal of county transportation planners — is being built through a public-private partnership with the developer, which the County Board authorized in the summer of 2020.

JBG Smith had initially proposed an underground entrance at the corner of 18th Street S. and Crystal Drive. As those plans came into focus last summer, however, they were estimated to cost Arlington County $123-$126 million, which far exceeded the county’s budget of $95 million.

So JBG Smith went back to the drawing board during the winter and came back with the idea to build the entrance at street level and save the county at least $13 million.

This Saturday, the Arlington County Board is slated to approve changes to its agreement with JBG Smith, giving the developer until September to further design an at-grade entrance. Under this scenario, fare gates and a manager’s kiosk would be at street level with primary access from 18th Street S. and secondary access from Crystal Drive.

“This alternative offers cost savings over the current design by significantly reducing the amount of excavation required, reducing the number of elevators from five to three, and removing the need to penetrate the station vault wall,” according to a county report. It also reduces the construction time by three months.

An at-grade entrance still meets county goals and has the support of the Washington Metropolitan Area Transit Authority, per the report.

“Both the Underground Entrance Design Concept and the At-Grade Alternative equally achieve the goals of adding capacity to meet future growth, creating a multimodal transportation hub, and improving access and accessibility to the Crystal City Metrorail Station from Crystal Drive,” the county said.

The change to the agreement will cost around $232,000 and bring the total cost of the design phase — funded by a $5 million Northern Virginia Transportation Authority grant — to $3.9 million.

County staff say there will be an update on the project for the public this spring. JBG Smith plans to submit a proposal based on the updated designs in October with the goal of County Board approval in November.

If members approve of the designs and cost estimates, construction could start in the winter of 2023 and end in the spring of 2025 — similar to the existing timeline. The project would be extended if the County Board asks the company, or county staff, to find someone else to do it for less money.

Ultimately, Arlington County is on the hook to oversee the project, as it agreed to get the second entrance online by 2025 as part of the incentive package to bring Amazon to Pentagon City, provided the state partially funded it.

The site of the future east entrance is also slated to see new retail, but JBG Smith has put redevelopment plans on hold due to the pandemic, the county says. The east entrance designs leave room to build the retail spaces later on.

As part of the stalled retail project, JBG Smith agreed to hand over land for a public open space called “Metro Market Square,” according to a memo from the developer. The company is working with the county to build this space concurrently with the entrance project.

A map of the east Crystal City Metro station entrance and proposed Metro Market Square open space (staff image)

Recent Stories

Morning Notes

Update on Delayed Rosslyn Development — “The approved Arlington County site plan setting up the eventual demolition of two obsolete office buildings — one home to the Deep Throat garage…

Good Wednesday evening, Arlington. Today we published articles that were read a total of 14291 times… so far. 📈 Top stories The following are the most-read articles for today —…

ARLnow has been providing independent, in-depth coverage of Arlington since 2010. We are committed to keeping readers informed about the issues that matter most to the community, including those that…

Residents of The Shelton, an affordable housing development in the Green Valley neighborhood, are raising concerns about property management and poor treatment of residents. They previously raised these same issues…

Please join us on Saturday, June 3, from 2 to 4 pm for the Glencarlyn Home Tour in Arlington’s historic Glencarlyn neighborhood.  Among the featured homes will be a sparkling new home by A&N Builders at 5604-4th St. South. The inviting front porch opens to a light-filled space featuring high ceiling, wood floors, gas fireplace,  Pella windows, Shrock cabinets, Quartz countertop, and JennAir appliances.  Doors from the family room open to a large covered porch with a few steps to the level, landscaped rear yard.  Upstairs, there are four bedrooms, three bathrooms, laundry room, and linen storage.  The big lower level has a rec room, gym space, and a fifth bedroom and bathroom plus even more storage.  After leaving the home, stroll to the Ball-Sellers home, the oldest residence in Arlington, the community gardens at the library, Carlin Hall, and the 94 acre Glencarlyn Park. A lovely way to while away a late spring afternoon.

Submit your own Announcement here.

Is home ownership a goal of yours in 2023? Now is the time to make it happen! Grab a (virtual) drink with the area’s top Real Estate experts, learn all about the home buying process and on how you can get $1,500 towards your closing costs immediately!

Did you know the average Arlington renter will spend $150K in 5 years of renting? Stop paying down someone else’s mortgage! Join us for a Rent vs. Buy Happy Hour on Wednesday, June 7th at 6 p.m. via Zoom. If this time doesn’t work, we also are offering times convenient for your schedule!

A lot has happened in the local market since the beginning of the pandemic. Sip on your drink of choice and learn from Northern Virginia, Arlington and Washingtonian Magazines top producing agents! We will discuss the latest market updates, the home buying process and rent vs. buy cost savings. Please RSVP by clicking here.

Call/text Manavi at 703-869-6698 with any questions!

Submit your own Announcement here.

Homebuying 101: Steps to Getting Pre-Approved

Are you ready to jump into homeownership or started considering it but don’t know where to start? Financial preparation is key when thinking about purchasing your first home and the first step to getting pre-approved.

Join ACFCU’s mortgage loan officers

4th of July Celebration & Fireworks

Treat yourself this Independence Day with a world-class, private 4th of July extravaganza at the Military Women’s Memorial – a premier National Capital Region site.

Great food, fun, and the best views of Washington DC’s spectacular fireworks display. Relax, enjoy,

×

Subscribe to our mailing list