Plans to build a bridge between Crystal City and DCA poised to take two steps forward

A plan for a pedestrian bridge between Crystal City and Reagan National Airport is headed to the Arlington County Board for endorsement this weekend.

Specifically, the Board is set to bless a girder-style bridge that will connect a future southern entrance to the Virginia Railway Express station at 2011 Crystal Drive to the airport’s Terminal 2. It is also slated to approve more funding for an engineering firm to further develop designs for the bridge, dubbed the CC2DCA multimodal connection.

“The goal of the project is to create an intermodal connection designed to meet the needs of a broad range of pedestrians, bicyclists, and micro-mobility users of all ages and abilities between the core of Crystal City, the Mount Vernon Trail, and DCA,” per a county report.

Currently, getting from Crystal City to DCA on foot or bike involves navigating a series of trails and crossings the county has previously described as “circuitous.”

“Once completed, the journey from the foot of the bridge to the newly constructed security checkpoint at DCA would be about 1,300 feet,” the National Landing Business Improvement District said in a pamphlet published last winter. “Once completed, the new CC2DCA Multimodal Connector would make National Landing the only downtown in the country with its main street within a comfortable 5-minute walk from a major airport.”

After endorsing the project on Saturday, the Board is set to approve a new $4.2 million contract with Boston-based civil engineering firm Vanasse Hangen Brustlin, Inc. (VHB) so it can begin drafting preliminary designs. This includes nearly $386,000 in contingency.

CC2DCA preferred alternative and limits of land disturbance (via Arlington County)

Although it may seem incremental, the county says these signs of progress are important milestones in the years-long project, which the county projects could be completed in 2028.

First, this step forward means that a conceptual design phase and environmental review process led by the civil engineering firm VHB are wrapping up.

The County Board approved its first contract with the engineering firm in the spring of 2021 for design work.

Since then, the county, VHB and state and federal agencies winnowed down 16 initial bridge and tunnel connections to a “preferred alternative” and a runner-up bridge proposal, both unveiled last October.

The county says the U.S. Army Corps of Engineers, the Environmental Protection Agency and the National Parks Service signed off on the “preferred alternative” this February.

Meanwhile, an environmental assessment was conducted because CC2DCA would use federal funding and possibly impact the GW Parkway and other land maintained by the National Park Service. Arlington County said in the report that it expects this assessment will be ready for public review this summer.

The timeline for the CC2DCA design development (via Arlington County, edited by ARLnow)

Lastly, it took a few months of negotiation for the county and the engineering firm to agree to a new contract for the next design phase. If the County Board approves the $4.2 million increase this weekend, study and design spending will reach $8.2 million.

This is entirely covered by $9.5 million in Congestion Mitigation and Air Quality (CMAQ) Improvement funds already allocated to the county. The federal government estimates the project’s total cost could be around $40 million.

Arlington County first identified the need for a better connection to the airport in 2010 but the project gained traction seven years later, when the National Landing BID pitched the idea and conducted a feasibility study.

In 2018, the state identified the bridge as one of five transportation projects it would partially or fully fund as part of its deal with Amazon, which is preparing to open the first phase of its second headquarters in nearby Pentagon City.

Recent Stories

After a several-month delay, 2910 Kitchen & Bar is gearing up to open next month on Columbia Pike pending final permit approvals, according to the restaurant owner.

More than 2,000 people have donated to the family who lost everything in the N. Burlington Street explosion, tripling initial fundraising goals.

Morning Notes

More on House Explosion Suspect — “The Virginia man presumed to have been killed when his house exploded while cops tried to serve a search warrant had posted rambling conspiracy…

Good Wednesday evening, Arlington. Let’s take a look back at today’s stories and a look forward to tomorrow’s event calendar. 🕗 News recap The following articles were published earlier today…

About Latinas Leading Tomorrow (LLT): Latinas Leading Tomorrow is a dynamic 501(c)(3) nonprofit organization dedicated to empowering young Latina women through education, mentorship, and leadership development. We are committed to fostering a community of future leaders who will make a significant impact to the community.

Job Description: We are seeking a passionate and dedicated Part-time Executive Director to lead our organization into its next phase of growth and impact. The ideal candidate will be a visionary leader who can oversee day-to-day operations, drive fundraising efforts, and cultivate relationships with stakeholders. This is a 1099 position; Remote position with ability to attend DMV events; 8-10 hours a week; $35-40/per hour.

Key Responsibilities:

Oversee program operations, including educational and community initiatives.
Ensure compliance with legal and regulatory requirements, maintaining trust and accountability.
Develop and execute a strategic vision aligned with our mission and values.
Lead fundraising efforts in partnership with the Board Members.
Cultivate relationships with community partners, schools, educators, and donors.
Demonstrate strong leadership skills, fostering a positive organizational culture.
Communicate effectively with diverse stakeholders and make compelling public presentations.
Promote inclusivity and collaboration throughout the organization.

Read More

Submit your own Announcement here.

Children’s Weekday Program (CWP) is a non-profit preschool rooted in a play-based philosophy. We focus on developing a love of learning and exploration, cooperation, empathy, and independence.

Our caring and experienced educators create opportunities for children 16 months to 5 years old to play, learn, and grow in a nurturing environment of child-centered and developmentally appropriate experiences.

Initially established more than 50 years ago in South Arlington, CWP continues to be a lauded program in the Northern Virginia area. We are extremely proud to have been recognized as a Best Preschool in Northern Virginia Magazine for the last 4 years.

Located now in North Arlington at 2666 Military Road, CWP offers a part-time parents day out and preschool program with options to extend care both before and after school. We offer a supportive and inclusive school community for children and parents alike and welcome all families to join our school!

Read More

Submit your own Announcement here.

Holiday Art Show

Holiday Art Show featuring artists: Peter Fitzgerald, Claire Plante, Alanna Rivera, and Suzy Scollon. At the Barcroft Community House, 800 South Buchanan St., Arlington, VA. Dec. 8 from, 2 PM to 8 PM and Dec. 9 from 10 AM to

Live Standup Comedy Starring Casey James Salengo (Jimmy Kimmel Live,…

Standup Comedy Starring Casey James Salengo (Comedy Central, Jimmy Kimmel Live)

Friday, December 29

Headliner: Casey James Salengo

Casey James Salengo is a NYC-based comedian who’s been featured on Comedy Central Presents, Jimmy Kimmel Live, This Week at the Cellar,

×

Subscribe to our mailing list