News

County Board to Consider Contract to Reconfigure Part of 23rd Street S.

Update at 1:40 p.m. — The County Board meeting scheduled for this weekend has been delayed until Saturday, April 25.

At its Saturday meeting, the Arlington County Board is set to consider a construction contract for upgrades to a portion of 23rd Street S. in Crystal City.

As part of the first phase of a two-phase project, the county is planning to “widen the sidewalk and retail parking areas on the south side of 23rd Street” between Route 1 and S. Eads Street. That will mean improved pedestrian safety and better ease of use for the existing parking lot that serves Young Chow restaurant, the Crystal City Restaurant gentlemen’s club, and 7-Eleven.

“Lane widths will be reduced, but the number of travel lanes will remain the same as today,” a county staff report says. “The new curb re-alignment will create more room for vehicles in the shopping plaza to maneuver without encroaching onto the sidewalk.”

Additionally, the $1.33 million construction contract will add new landscaping, crosswalks, ADA-accessible curb ramps and upgraded traffic signals at the intersection of 23rd and Eads. The overall project cost for Phase 1 is about $2.1 million, which will be funded by a regional Northern Virginia Transportation Authority grant.

“Upon approval by the county board, construction is expected to begin Summer of 2020 and to be complete in Winter of 2021,” says the staff report.

Phase 2 of the project is still in design but is expected to upgrade 23rd Street S. between Route 1 and Crystal Drive, with new sidewalks and trees on either side, while removing the grassy median in the middle. That project being planned in conjunction with JBG Smith’s major redevelopment project on the north side of 23rd Street.

“Phase 2 of the project is anticipated to implement similar improvements on 23rd Street South east of Richmond Highway to Crystal Drive,” the staff report notes. “Phase 2 is currently in 30% design and is being coordinated with private sector redevelopment efforts along 23rd Street South.”

The stretch of 23rd Street S. between Arlington Ridge Road and Crystal Drive, which includes the Crystal City’s well-known restaurant row, is seeing a series of infrastructure changes as Amazon arrives in the neighborhood. A project to replace a major water main along 23rd Street is currently underway, and the county recently finished closing an underground pedestrian tunnel under Route 1.

Separately, the County Board on Saturday will also take up the renaming of the Crystal City Business Improvement District to the “The Crystal City, Pentagon City, and Potomac Yard at National Landing Business Improvement Service District.”

Street view via Google Maps