Starting this spring — as soon as final regulatory approvals are issued — crews will begin work on the first of eight construction phases that will stretch through August 2015. During that first phase, a detour will be constructed, using the north interchange ramps to provide a signalized, at-grade intersection on Washington Boulevard.
That detour is expected to be used for 3 to 5 weekends per year, starting this summer, when crews need to shut down Columbia Pike for demolition of the existing Washington Boulevard bridge and construction of a pair of new spans, just east of the existing bridge. The detour will also include facilities for pedestrians.