VDOT has kicked off work on its I-66 Rosslyn Tunnel Rehabilitation project.
The nearly $38 million project is expected to stretch well into 2025, retrofitting the tunnel under Rosslyn’s Gateway Park that was built some 40 years ago.
The construction will prompt some lane closures on I-66, but mostly during overnight hours.
More from a VDOT press release:
Construction is underway on the rehabilitation and improvements to the Rosslyn Tunnel that carries I-66 under North Nash Street, Fort Myer Drive, North Lynn Street and Gateway Park, according to the Virginia Department of Transportation. The project’s purpose is to improve safety and extend the overall life of the tunnel.
The project includes removing the existing tunnel ceiling to improve long-term maintenance; upgrading electrical systems; installing a new fireproofing system; repairing steel beams, abutment and pier concrete, and joints; cleaning and repairing bearings; and replacing the tunnel lighting system.
Lane closures on I-66 associated with the project will mainly occur overnights, with at least one lane of I-66 in each direction open at all times.
The tunnel, which opened to traffic in 1983, is nearly a fifth of a mile long and averages 64,000 vehicles a day.
The $37.7 million project is financed with state funding and is scheduled for completion in summer 2025.
For the most recent updates and to learn more, visit the VDOT project webpage.
Drivers, cyclists and pedestrians are reminded to use caution when traveling in active work zones. Be alert to new traffic patterns and limit distractions.
You can get real-time traffic, work zone and incident information online at 511virginia.org, via the free mobile 511Virginia app, or by calling 511 in Virginia anywhere anytime.
Construction is starting next week to make Boundary Channel Drive and the I-395 interchange near Crystal City and the Pentagon safer.
The impact on locals should be “minimal,” Virginia Department of Transportation spokesperson Mike Murphy told ARLnow. While there could be lane closures, access to surrounding facilities will be kept open.
“Some day and overnight lane closures may be scheduled along I-395, Boundary Channel Drive, and Long Bridge Drive in the project area,” Murphy said. “Access to I-395 via Boundary Channel Drive, as well as access to Pentagon facilities and the Long Bridge Aquatics & Fitness Center will be maintained during construction.”
The long-planned $20 million project is set to reduce traffic lanes on Boundary Channel Drive to make room for paths and sidewalks, install roundabouts, reconfigure ramps, and add crosswalks.
The purpose of the renovations is to simplify traffic patterns and to make it safer for pedestrians, cyclists and drivers.
“We’ve long sought these improvements,” then-County Board Chair Matt de Ferranti said at a Board meeting last year when voting to approve the project. “They will reconfigure the interchange that you see to make it work a lot better and safer for everyone.”
The VDOT-led project is expected to be completed about a year from now, in fall 2023.
Crews will begin with work on Boundary Channel Drive, where both directions will be reduced to one lane to allow for the construction of the new roundabouts, utility work, and pedestrian improvements.
Those improvements include a path along the south side of Boundary Channel Drive, complete with crosswalks, landscaping, and street lighting.
The new shared-use path, varying in width between ten and twelve feet, will start at the Long Bridge Aquatic Center parking lot entrance. It will then follow Long Bridge Drive northbound before connecting with westbound Boundary Channel Drive, per Murphy. The half-mile-long path will pass under I-395 and turn north at the soon-to-be-built western Boundary Channel Drive interchange roundabout.
The new path will ultimately connect with the existing one that parallels the southbound George Washington Memorial Parkway ramp to I-395 southbound.
This project has been in the works since at least 2014 and is estimated to cost $19.6 million. It’s being paid for by a combination of state, federal, regional, and county money.
The 21st Street N. bridge over I-66 is set to get a minor makeover.
The bridge — located north of Courthouse, near the MOM’s Organic Market — was built in 1980 and carries around 1,400 vehicles per day. It was described as “deteriorating” in a project review carried out by the Virginia Department of Transportation in 2017.
VDOT plans to resurface the concrete bridge deck, close the deck joints, repair the concrete piers and abutments of the bridge, as well as replace its bearings, according to a news release. The project is not expected to change the width of the existing lanes and sidewalks on the bridge, which is also located near McCoy Park.
Construction is scheduled to begin next summer. The work is not expected to close any existing roads that may significantly disrupt traffic, according to the project’s website, and should improve the bridge’s safety and longevity.
The estimated cost is $3.4 million, which is paid for by federal and state funds, including money from Virginia’s State of Good Repair program, VDOT said.
A virtual public meeting is set for 7 p.m. tomorrow (Tuesday), during which the project team is scheduled to give a presentation and answer questions from the audience.
Those interested in participating can register for the meeting on the project website beforehand. Those who do not register can instead call 1-866-901-6455 to listen in on the meeting, according to VDOT.
After the meeting, interested members of the public will be able to voice their opinions on the project through an online form, email or U.S. Mail. The public comment period is set to end on Monday, July 11.
Map via Google Maps
School’s Out for Summer — Today is the last day of high school for Arlington Public Schools students. Tomorrow is the last day of middle school and Friday is the last day of elementary school. [Arlington Public Schools]
Meetings Planned for Route 1 Changes — “Two upcoming online forums will look at Virginia Department of Transportation proposals for U.S. Route 1 through the Crystal City corridor. On June 15 at 7 p.m., the Livability 22202 Route 1 Working Group and VDOT proposals will be presented and feedback sought… On June 21 at 6:30 p.m., VDOT will host a public-information meeting on the proposal.” [Sun Gazette, VDOT]
Yorktown Girls Win State Soccer Tourney — “A season that began with a loss ended with no other setbacks and a state championship for the Yorktown Patriots. The girls soccer team won the Virginia High School League Class 6 state tournament by nipping the Kellam Knights, 1-0, in the June 11 title game.” [Sun Gazette, Washington Post]
DJO Softball Wins State Title — “The [Bishop O’Connell] Knights capped a dominant campaign with their 26th Virginia Independent Schools Athletic Association state title over the past 28 seasons. Katie Kutz tossed 235 strikeouts and went 17-0 while batting .482 at the plate en route to Washington Catholic Athletic Conference and VISAA player of the year nods.” [Washington Post]
Groundbreaking for Bus Maintenance Yard — “Arlington County will host a groundbreaking ceremony Wednesday morning for its new Arlington Transit (ART) operations and maintenance facility. The public is invited to attend. The ceremony will take place at 10 a.m. at the site of the future facility at 2629 Shirlington Rd. in Arlington in the Green Valley neighborhood.” [Patch]
School Board Absences — “The board, whose schedule of meetings is approved at the start of each fiscal year, has had a tough time gathering all five members on the dais at one time in recent months. Goldstein frequently has been absent, and at the May 26 meeting Priddy was gone. (On May 26, Diaz-Torres was not attending in person but did participate remotely from Puerto Rico, Kanninen said at the start of that meeting.)” [Sun Gazette]
More Bad Driving on I-395 — From Dave Statter: “This is a new one. Driver just stops at the end of the gore partially blocking the left lane until they can figure out their next move.” [Twitter]
Gov. Proposes Three-Month Gas Tax Holiday — “In Arlington, Virginia, the cost of regular gas is around $5.29. As gas prices continue to climb, CG Green says he’s pumping the brakes on unnecessary trips. ‘Look at it, it’s crazy,’ said Green. ‘It’s $5.29 for gas. I have to rethink where I’m going.’ Virginia Governor Glenn Youngkin says he is in favor of temporarily suspending the commonwealth’s gas tax.” [WUSA 9]
It’s Wednesday — Partly cloudy throughout the day. High of 86 and low of 68. Sunrise at 5:44 am and sunset at 8:37 pm. [Weather.gov]
Members of Congress from Virginia are pushing the federal government to help fund proposed changes to Route 1.
The changes, while still being hashed out by VDOT and local officials, would lower elevated portions of Route 1 through Crystal City to grade, turning it into a lower-speed “urban boulevard.” VDOT is also mulling at least one pedestrian bridge or tunnel at 18th Street S., near the Metro station, to improve safety.
With the first phase of Amazon’s HQ2 on track to open in Pentagon City in 2023, state and local officials see a need to turn the area — collectively known as National Landing — into a more cohesive downtown and economic center. Key to that vision is revamping Route 1, also known as Richmond Highway, which effectively separates Pentagon City from Crystal City.
At last check, cost estimates for the project were around $200 million.
Northern Virginia’s congressional delegation would like to see the feds foot much of the bill, through funding from the 2021 bipartisan infrastructure bill.
In a joint letter to Secretary of Transportation Pete Buttigieg, the lawmakers say argue that the Route 1 project meets all criteria for funding through the infrastructure bill.
“This grant request will allow Virginia to convert the Route 1 corridor in Arlington into a multimodal urban boulevard that prioritizes pedestrian safety in a walkable environment,” the wrote. “VDOT is developing multimodal solutions for Route 1 to meet National Landing’s transportation needs with the coming of Amazon and other related developments.”
The letter was signed by Sens. Tim Kaine (D-Va.) and Mark Warner (D-Va.), along with Reps. Don Beyer (D-Va.), Abigail Spanberger (D-Va.), Donald McEachin (D-Va.), Elaine Luria (D-Va.), and Robert Wittman (R-Va.).
“The Commonwealth’s commitment to Amazon is to improve safety, accessibility, and the pedestrian experience crossing Route 1,” the lawmakers wrote. “Investment in National Landing will produce significant, measurable benefits to the economy, health, and safety of local citizens… This project satisfies all the merit criteria outlined in the federal grant opportunity, especially the priorities of providing economic, state of good repair, environmental, and equity benefits.
The letter also argues for the project’s fiscal benefits, including reducing bridge maintenance costs and providing acres of additional land for development.
“The transformation of Route 1 to an urban boulevard includes the removal of three bridge structures from the VDOT inventory, which will reduce long term maintenance costs,” the letter said. “Modifications to the I-395 interchange will remove a structurally deficient bridge and avoid future replacement or rehabilitation costs, while also extending the urban boulevard to the north which will contribute to lower speeds.”
“[The project] increases the accessibility to job centers through the proposed access improvements, which will benefit residents of all income levels,” the letter continues. “The project will create approximately 6.5 acres of excess right-of-way resulting in high value developable land.”
Another hoped-for benefit: fewer cars and better safety features.
“It will reduce the need for single-occupancy vehicle trips in favor of environmentally friendly options such as enhanced transit service, walkability, biking routes,” said the letter. “The project also includes multiple innovative solutions, such as a progressive design-build strategy and a pilot safety project to implement near-miss crash technology in National Landing.”
The completion of VDOT’s Phase 2 study of the proposed changes is currently expected to wrap up in early 2023. While the project has general support from the county and the business community, some residents have expressed concerns about whether taking away overpasses in favor of at-grade crossings actually makes things more dangerous for pedestrians.
Much of the congressional delegation, led by Kaine, also wrote a letter to Buttigieg supporting funding for an I-64 connector to ease congestion between Richmond and Hampton Roads.
A rehabilitation project and a potential lane reconfiguration are both in the works for the S. Abingdon Street bridge in Fairlington.
The bridge, which carries local vehicle and pedestrian traffic in the neighborhood over I-395, was built in 1970 and last rehabilitated in 1994. It’s due for more work to improve safety and extend the bridge’s life, VDOT says.
A VDOT presentation noted that inspectors found crumbling concrete below the bridge span.
The state transportation department is conducting a virtual public engagement process about the upcoming $10.5 million rehab project, for which it anticipates starting construction in the summer of 2023. At least one lane of vehicle and bike traffic will be maintained in each direction during construction, VDOT says.
More from VDOT’s website, below.
The project includes:
- Resurfacing the concrete bridge deck and closing deck joints
- Repairing concrete piers and abutments
- Adding protective concrete barriers adjacent to piers
- Extending and adding concrete in-fill walls between piers
- Replacing bearings and reconstructing bearing seats
The existing sidewalks on both sides of the bridge will remain and the bridge bicycle lanes will be restriped as part of the project.
The bridge averages 8,300 vehicles a day based on 2019 data.
The project is financed with federal and state funding.
Get Involved
In lieu of an in-person meeting, VDOT invites residents and travelers to learn more, watch the virtual presentation and give feedback in the following ways through Wednesday, June 1:
- Watch the virtual presentation (also available in Chinese and Spanish) at virginiadot.org/Abingdon395.
- Provide comments via the online survey or by email to [email protected].
- Mail comments to Mr. Sharif Ramsis, P.E., Virginia Department of Transportation, 4975 Alliance Drive, Fairfax, VA 22030.
In addition to VDOT’s construction project, Arlington County is gearing up for a “Complete Streets” repaving and re-striping project on the bridge — from Fire Station 7 to 34th Street S. — this summer.
The project may involve removing the sparsely-used street parking on either side of the bridge, in favor of more robust and protected bike and pedestrian facilities, based on public comments and past history with the program.
Several comments note concerns about vehicles speeding on the bridge and the presence of students going to and from school.
An exact plan for the county’s Complete Streets project has yet to be published.
Photo via Google Maps
VDOT is not turning back on its recommendation to lower the elevated parts of Route 1 in Crystal City, but it is considering new options for separated pedestrian and bike crossings near the Metro station.
The state transportation agency on Thursday provided an update on Phase 2 of its study, which is focused on how to make the “urban boulevard” vision for Route 1 from 12th Street S. to 23rd Street S. a reality.
VDOT unveiled concepts for alternatives to a street-level pedestrian crossing at 18th Street after its recommendation to lower elevated portions of Route 1 drew ire from the community for prioritizing cars over pedestrians.
Four alternatives to the at-grade pedestrian crosswalks at 18th Street S. were presented, including a pedestrian bridge; a more gradual, bicycle-friendly bridge; a tunnel; or an underpass.
While the options incorporate some public feedback, including the tunnel proposed by community group Livability 22202, the state is focused on finding a way to make the at-grade roadway work.
“Everything that happens in the Phase 2 study is really looking from that lens of having made that recommendation already and Phase 2 is really geared towards figuring out the details of how to make that recommendation from Phase 1 work,” said Dan Reinhard, VDOT’s lead project manager for the project.
The first phase of VDOT’s study recommended the elevated portions over 12th, 15th and 18th streets be lowered and Phase 2 examines the feasibility of doing that, what traffic in the area looks like and strategies to reduce vehicular traffic.
The first alternative to at-grade crossings is a 12-foot-wide pedestrian bridge with stairs and an elevator option. VDOT estimates this would cost $15 million.
The second bridge alternative, at an estimated $32 million, would add more gradual entry points for cyclists on 18th Street S. This option could link with a multimodal trail that the county plans to build near the Crystal City Metro station, said John Martin, with engineering consulting firm Kimley-Horn.
The third concept, a tunnel under Route 1, was informed by Livability 22202, a coalition of the Arlington Ridge, Aurora Highlands, and Crystal City civic associations. The estimated $43 million tunnel would accommodate both bicyclists and pedestrians, connecting them to the Crystal City shops and the Metro.
The final alternative is a 12-foot-wide pedestrian and bicycle underpass. In coordination with building owners of the plaza at the corner of Route 1 and 18th Street S., the tunnel could feature a public space at its east entry. An underpass is estimated to cost between $9 million and $14 million.
VDOT also presented two options to ease navigation of the sometimes chaotic 23rd Street S. intersection.
At 23rd Street S., VDOT imagines windening pedestrian spaces and medians, removing one southbound left turn lane and allowing through traffic in the northbound right turn lane. A second option would also add bike lanes on the west side of 23rd Street S.
A second public meeting is expected in mid to late June, which will workshop the curb elements of street design and discuss potential relocation of 18th Street bus stops.
A third will be held in September or October and discuss ways to reduce vehicle volumes through Transportation Demand Management strategies. A final meeting will review the findings and recommendations.
Another Vehicle Larceny Series — “28th Street S. at 26th Street S./28th Street S. at S. Lang Street. At approximately 9:05 a.m. on April 25, police were dispatched to multiple reports of destruction of property. During the course of the investigation, it was determined that the unknown suspect(s) broke the windows to five vehicles and rummaged through them. One victim reported having electronics stolen from their vehicle. There is no suspect(s) description.” [ACPD]
Update on Route 1 ‘Urban Boulevard’ Plan — “The Virginia Department of Transportation (VDOT) will hold a virtual public information meeting Thursday, April 28 on a feasibility study identifying enhanced multimodal connectivity and accommodations along Route 1 (Richmond Highway) from 12th Street South to 23rd Street South to meet the changing transportation needs of the Crystal City and Pentagon City communities.” [VDOT]
More Wins for Yorktown Lax — “The defending state champion Yorktown High School boys lacrosse team improved to 7-2 with blowout victories over Herndon, 15-2, and Dominion, 17-5, for seven straight victories.” [Sun Gazette]
Regional Grant for Ballston Metro Entrance? — From Arlington’s Dept. of Environmental Services: “A new west entrance to the Ballston-MU Metrorail station is in the running. Let these fine folks know why their greenbacks would be well spent.” [Twitter, N. Va. Transportation Authority]
‘Empty the Shelters’ Event Next Week — “The Animal Welfare League of Arlington is participating in the Bissell Pet Foundation’s spring “Empty the Shelters” animal adoption event next week from May 2-8. More than 275 shelters in 45 states and Canada are participating in the week-long event. The Bissell Pet Foundation sponsors reduced adoption fees for $25 or less.” [Patch]
Warner Weighs in on Musk Buying Twitter — From Sen. Mark Warner: “Elon Musk must work in good faith to preserve Twitter’s necessary reforms to prevent the spread of misinformation.” [Twitter]
It’s Wednesday — Mostly sunny, with a few more clouds in the afternoon. High of 58 and low of 44. Sunrise at 6:16 am and sunset at 7:58 pm. [Weather.gov]
A 50-year-old bridge over I-395 near Shirlington is slated for upgrades next year.
Locals can learn more about the planned bridge work next Tuesday evening during a virtual meeting hosted by VDOT, which is managing the project.
The bridge connects the southbound I-395 collector-distributor lanes and southbound Shirlington Road to N. Quaker Lane at the I-395 Exit 6 interchange.
First constructed in 1973, the bridge needs upgrades to improve safety for drivers and to extend its usable lifespan, says VDOT. Today, the bridge is crossed by about 7,400 vehicles daily.
According to the project webpage, VDOT will:
- Resurface the concrete bridge deck and closing deck joints
- Repair concrete piers and abutments
- Repair and repaint steel beams
- Add protective concrete barriers adjacent to piers
- Replace bearings
- Upgrade guardrails adjacent to the bridge
The $4.3-million project will be financed with federal and state funding, including State of Good Repair funds used for bridges.
Next Tuesday’s meeting will begin at 7 p.m. VDOT staff will make a short presentation and then answer questions from the public for an hour. Project materials, which are not yet available, will be posted on the meeting webpage before the meeting starts, the department says.
Through Friday, March 25, VDOT will accept feedback via email and U.S. mail, addressed to Vicente Valeza, Jr., P.E., Virginia Department of Transportation, 4975 Alliance Drive, Fairfax, VA 22030.
As locals eat their lunch, all eyes are on the skies. Snow — likely heavy snow — is about to start falling in Arlington.
County and state crews say they’re ready to tackle what’s expected to be a messy mix of precipitation throughout the day: snow to start, freezing rain as the sun sets, and then plain rain as temperatures warm after nightfall, before perhaps a brief changeover back to soggy snow in the early morning hours.
The snowfall may start with a bit of a bang.
We are watching a heavy snow band progressing northwards as the storm is starting for many of us. Will lead to reduced visibility at times, especially in the DC Metro. pic.twitter.com/bZYe9l8Wxa
— Washingtonian Weather Geeks (@WashingtonianWx) January 16, 2022
In Arlington and across the region, main roads, bridges and highways have been pre-treated with brine ahead of the snowfall. VDOT says it has 3,800 pieces of equipment set to deploy in Northern Virginia during the storm.
“VDOT Northern Virginia crews are mobilizing for snow, freezing rain, and rain that is forecasted to significantly impact the region Sunday and Monday,” the state transportation agency said today. “Crews began the mobilization process Sunday morning. As always, residents are asked to monitor forecasts, plan ahead to avoid nonessential travel during winter weather, and to be aware of the potential for black ice and nightly refreeze as temperatures remain low.”
Arlington County is also encouraging residents to stay at home and off the roads as conditions deteriorate.
https://twitter.com/readyarlington/status/1482738996816101380?s=21
The county has about 40 trucks ready for its snow response. Typically, crews focus on primary and secondary routes to start, then start plowing neighborhood streets later.
First shift of County storm response begins at noon with some 40 trucks ready. For safety and effectiveness, plan to stay off roads until hours after the winter weather event has passed. #ArlWX https://t.co/DuInmBchJW pic.twitter.com/k7cItKR13N
— Arlington Department of Environmental Services (@ArlingtonDES) January 16, 2022
This morning, in anticipation of the storm, Arlington’s Dept. of Parks and Recreation announced that community centers would be closed today, while the Long Bridge aquatics center would close early.
From DPR:
Arlington Mill, Lubber Run and Thomas Jefferson Community Centers, which were scheduled to open at 1 p.m. today, will remain closed. Long Bridge Aquatics & Fitness Center, which opened at 8 a.m. today, will close at 1 p.m.
All virtual programs will continue as scheduled, including the 53rd Tribute to Rev. Dr., Martin Luther King Jr.
You can also stay engaged by enjoying the snow in one of our parks or trails. Want to stay inside? Check out our YouTube stations for options to be active and have fun for people of ages and interests.
Please stay safe.
A Winter Weather Advisory is in effect for Arlington and the immediate D.C. area.
From the National Weather Service:
…WINTER WEATHER ADVISORY REMAINS IN EFFECT FROM 1 PM THIS AFTERNOON TO 1 AM EST MONDAY…
* WHAT…Mixed precipitation. Additional snow accumulations of 1 to 3 inches and ice accumulations of around one tenth of an inch. Winds gusting as high as 45 mph.
* WHERE…Portions of The District of Columbia, central, north central, northeast and northern Maryland and northern Virginia.
* WHEN…From 1 PM this afternoon to 1 AM EST Monday.
* IMPACTS…Plan on slippery road conditions.
PRECAUTIONARY/PREPAREDNESS ACTIONS…
Slow down and use caution while traveling.
When venturing outside, watch your first few steps taken on steps, sidewalks, and driveways, which could be icy and slippery, increasing your risk of a fall and injury.
First County Board Meeting of 2022 — “Arlington County Board members will hold their annual organizational meeting on Monday, Jan. 3 at 6 p.m… At the meeting, board members will elect a chair for the coming year (almost assuredly Katie Cristol) and will lay out their own personal priorities for the coming year. A number of procedural votes will be held, but the real business of governance will not take place until the board’s formal January meeting later in the month.” [Sun Gazette]
Bridge Project Near Fairlington Complete — “The rehabilitation of the King Street (Route 7) bridge over I-395 and pedestrian improvements along a half-mile of King Street are complete, Virginia Department of Transportation officials said on Dec. 22, improving pedestrian mobility and safety, giving drivers a smoother ride and extending the overall life of the bridge. The $13 million project was financed with federal and state funding.” [Sun Gazette]
It’s Monday — A chance of rain and snow flurries before 9 a.m. today, then rain likely through the afternoon. Otherwise cloudy, with a high near 44. Sunrise at 7:26 a.m. and sunset at 4:53 p.m. Tomorrow there’s a chance of rain after 1 p.m., but otherwise it will be cloudy with a low of 41 and a high of 52. [Weather.gov]