The updated plan calls for reducing the size of the facility by 37 percent. That will reduce the overall cost of the project — which also includes the development of 10.5 acres of parkland around the facility — by 17 percent. The cost of the smaller facility is estimated at $63-67.5 million.
The goal is to reduce the cost of the project to within the $64 million in financing already obtained, primarily through a bond issue and developer contributions. The project was put on hold after construction bids well exceeded the original $79.2 million budget, as included in the county’s Capital Improvement Plan.